PLM07-00127 Plumbing Rough-in1/18/20071/18/20071/18/2007 4:47:26 PMPPASS
Scheduled by a contractor via Hello! on 1/18/2007 at 8:48:39 AM. Contact: ###-####.
PLM06-03857 Plumbing Rough-in1/18/20071/18/20071/18/2007 4:26:12 PMPPASS
Phone #: ###-####
PLM07-00137 Water and/or Sewer1/17/20071/18/20071/18/2007 3:51:15 PMPPASS
Jay is contact for this job 573.6120
PLM07-00137 DOC - Permit Finaled1/18/20071/18/20071/18/2007 3:50:46 PMPPASS
Jay is contact for this job 573.6120
sewer replaced...ds
PLM06-03882 Final1/18/20071/18/20071/18/2007 3:31:06 PMPPART
Back flow needs tested and certified....temp occ ok...ds
PLM07-00053 Plumbing Rough-in1/18/20071/18/20071/18/2007 2:30:47 PMPPASS
Scheduled by a contractor via Hello! on 1/18/2007 at 8:41:36 AM. Contact: ###-####.
PLM06-04176 Plumbing Rough-in1/17/20071/18/20071/18/2007 2:20:44 PMAFAIL
Phone #: ted ###-####
need to change some plg and obtain a ele permit...ds
PLM06-03209 Final1/18/20071/18/20071/18/2007 1:48:14 PMPPASS
If locked call Scott with Fidelity for access ###-####. Phone #: ###-#### x0113
PLM07-00080 Plumbing Rough-in1/17/20071/18/20071/18/2007 11:23:08 AMAPART
On site contact Corry @ ###-####. Job#601 Phone #: ###-####
R/I for sink in basement pharmacy...ds
PLM06-02342 Final1/17/20071/18/20071/18/2007 10:51:49 AMAPASS
Scheduled by a contractor via Hello! on 1/17/2007 at 4:37:07 PM. Contact: ###-####.
PLM06-02313 Final1/17/20071/18/20071/18/2007 10:16:01 AMAPASS
Contact: Dan or Linda Inspection must be made in the A.M.--Floors to be coated in the P.M. Phone #: ###-####