Inspections for the day of: Friday, January 18, 2019.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMark Moncarr
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE13-03258 ELE-Aging Inspection1/18/20191/18/20191/23/2019 5:25:56 AM PASS
Schedule a final inspection
ELE19-00168 Final1/18/20191/18/20191/18/2019 2:09:21 PMPPASS
Container Home - permanent service 200 amp // Jay Phone #: ###-#### Ok final. I have mentioned in the past that if work being done is a permanent service, and service inspection needs to be requested, not a final. Next time, a fail with a re-inspect fee will apply.
ELE19-00168 Permanent Service1/18/20191/18/20191/18/2019 2:04:02 PMPPASS
Jay ###-#### p/s u/g n ok
ELE18-04262 Final1/18/20191/18/20191/18/2019 2:03:42 PMPPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Ok final. Floor box installed. I was able to test good power to recepts.
ELE19-00059 Final1/18/20191/18/20191/18/2019 2:03:07 PMPPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Ok final. Table set in conf room. Unable to test recepts due to lack of room. Talked to electrician, said he tested good on recepts.
ELE18-04243 Final1/17/20191/18/20191/18/2019 2:00:28 PMPPASS
Please call homeowner Dave Bruce before heading to house. Phone number ###-#### Phone #: ###-#### Inspection requested via web by Dean Gernaat Ok final.
ELE18-02961 Electrical Rough-In1/14/20191/18/20191/18/2019 2:00:08 PMAPASS
Phone #: ###-#### Inspection requested via web by Elizabeth Gawle Ok cover. New power for island is in box. Once island set, wire will stub up through bottom of cabinet.
ELE18-04102 Final1/17/20191/18/20191/18/2019 11:42:37 AMAPASS
She will be home. If you have any questions please feel free to contact Darren ###-####. Thanks!!! Phone #: ###-#### Inspection requested via web by Clayton Morgan Ok final.
ELE19-00185 Electrical Rough-In1/18/20191/18/20191/18/2019 11:12:00 AMPPASS
Lloyd ###-#### Homeowner. Ok cover ceiling, and all other walls except where work is being done. 10/3 junction point to left of utility door needs open for inspection.
ELE19-00185 Conference1/17/20191/18/20191/18/2019 11:10:50 AMADONE
Lloyd Phone #: ###-#### Discussed required outlets needed after closet is built. 10/3 UF spiced in wall left of door going into utility. Needs to be open upon RI inspection to verify correct junction or removal of wire. Also discussed load calc since adding 30a mini split circuit. Panel is full.
ELE19-00210 Final1/17/20191/18/20191/18/2019 10:24:02 AMAFAIL
Phone #: ###-#### Inspection requested via web by Ryan Wilson
1. 334.12(B)(4) NM cable in damp location.
2. 210.63 Service recept required.
ELE19-00209 Final1/17/20191/18/20191/18/2019 10:23:09 AMAFAIL
Phone #: ###-#### Inspection requested via web by Ryan Wilson
1. 334.12(B)(4) NM cable in damp location.
2. 210.63 Service recept required.
ELE19-00212 Rough-In Permanent Service1/17/20191/18/20191/18/2019 10:20:52 AMAPASS
Phone #: ###-#### Inspection requested via web by Greg Idsinga p/s u/g n ok
ELE19-00137 Final1/17/20191/18/20191/18/2019 8:50:08 AMAPASS
Phone #: ###-#### Inspection requested via web by Ryan King Ok final.