ELE18-02816
| Conference | 1/18/2019 | 1/18/2019 | 1/18/2019 3:41:27 PM | P | PASS |
|
|
Need inspection for bringing existing building up to code. Phone #: ###-#### Inspection requested via web by Kotton Corder... walked job with journeyman on site discussed work done and current code violations still existing Building wiring shall be wired as Class II Division I codes
|
ELE18-04697
| Rough-In Permanent Service | 1/18/2019 | 1/18/2019 | 1/18/2019 2:19:34 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Krista Ratterree.... service switch gear and grounding installed by others underground and wire feeds done by contractor p/s u/g new ok
|
ELE19-00173
| Permanent Service | 1/15/2019 | 1/18/2019 | 1/18/2019 1:40:02 PM | P | PASS |
|
|
This work has been coordinated with Idaho Power to disconnect power at 9am. Work will be completed and ready to inspect by early afternoon 1-2. Please contact Tyson to coordinate a time to inspect this panel upgrade so we can restore power to the residence in a timely manner. Phone #: ###-#### Inspection requested via web by Tyson Dye... p/s reconnect ok
|
ELE19-00158
| Final | 1/18/2019 | 1/18/2019 | 1/18/2019 1:13:30 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Matthew White... outlet added in ceiling for pool table light ok to final
|
ELE19-00187
| Final | 1/18/2019 | 1/18/2019 | 1/18/2019 12:23:48 PM | P | PASS |
|
|
final for TV cabinet...no further inspections needed...ok to final
|
ELE19-00186
| Final | 1/18/2019 | 1/18/2019 | 1/18/2019 12:23:14 PM | P | PASS |
|
|
final for TV cabinet...no further inspections needed...ok to final
|
ELE19-00222
| Final | 1/18/2019 | 1/18/2019 | 1/18/2019 12:19:52 PM | P | PASS |
|
|
final and permanent service for cable t v power supply .located at s e corner of 3021 n ash park ln .contact #2088694390 Andy. Phone #: ###-#### Inspection requested via web by andrew dopieralski... no other inspection needed...ok to final
|
ELE19-00222
| Rough-In Permanent Service | 1/18/2019 | 1/18/2019 | 1/18/2019 12:19:24 PM | P | PASS |
|
|
final and permanent service for cable t v power supply .located at s e corner of 3021 n ash park ln .contact #2088694390 Andy. Phone #: ###-#### Inspection requested via web by andrew dopieralski.... p/s u/g new ok
|
ELE18-04660
| Final | 1/17/2019 | 1/18/2019 | 1/18/2019 11:46:54 AM | A | PART |
|
|
Partial Final Phone #: ###-#### Inspection requested via web by Kerri Hamilton... partial to give temp occupency to move furniture in but no business to take place remaining...all cubicles installed and power hooked up, missing blank, power to 2 offices outlets
|
ELE18-03046
| Final | 1/17/2019 | 1/18/2019 | 1/18/2019 11:11:52 AM | A | PASS |
|
|
Please call an hour in advance to have homeowner let inspector in // Mike Phone #: ###-####...ok to final
|
ELE18-04697
| Final | 1/17/2019 | 1/18/2019 | 1/18/2019 10:16:09 AM | A | FAIL |
|
|
Rhonda Phone #: ###-####... no rough inspection was performed on service or work...unable to verify grounding at service, generator, and transformer...AFC label needs applied to service...a rough permanent service inspection is required before a final can be scheduled
|
ELE19-00046
| Final | 1/17/2019 | 1/18/2019 | 1/18/2019 9:59:23 AM | A | PASS |
|
|
Adam Jr Phone #: ###-####... labelling, disconnect, and OCPD ok to final
|
ELE19-00217
| Final | 1/17/2019 | 1/18/2019 | 1/18/2019 9:42:43 AM | A | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Don Conley.... final can not be done until power is restored to space and work complete
|
ELE19-00217
| Permanent Service | 1/17/2019 | 1/18/2019 | 1/18/2019 9:41:53 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Don Conley.... power off for over yr p/s u/g reconnect ok
|
ELE19-00208
| Final | 1/17/2019 | 1/18/2019 | 1/18/2019 9:12:46 AM | A | PASS |
|
|
installed outlet for gas range. Tenant home in morning. Jason is our contact. Thank You! Phone #: ###-#### Inspection requested via web by Kelly Felin... use of existing 240v circuit to 2 110 circuits... ok to final
|
ELE19-00197
| Temporary Service | 1/17/2019 | 1/18/2019 | 1/18/2019 8:57:25 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Dean Gernaat... t/s u/g new ok
|
ELE19-00204
| Temporary Service | 1/17/2019 | 1/18/2019 | 1/18/2019 8:16:56 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Darryn Coburn.... 1...1 ground rod shall be driven for temp service 2..service ground shall be installed to ground rod
|
ELE19-00198
| Rough-In Permanent Service | 1/17/2019 | 1/18/2019 | 1/18/2019 8:15:37 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Greg Traudt... rough ok to cover p/s u/g new ok
|
ELE18-04183
| Electrical Rough-In | 1/11/2019 | 1/18/2019 | 1/15/2019 3:24:08 PM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Laurie Hoelscher Inspection cancelled from web by: Laurie Hoelscher
|