Inspections for the day of: Wednesday, January 19, 2000.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-01076 BLD-Foundation1/18/20001/19/20001/19/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 01/18/2000 at 13:22:15. Contact: ###-####. Masonry-bar in place- ok to grout. 1/19/00 1:40:53 PM
BLD99-02714 BLD-Final1/18/20001/19/20001/19/2000 12:00:00 AMAFAIL
rob-- ###-#### fn occ Recall. 1/19/00 1:39:49 PM
BLD00-00002 BLD-Footing1/18/20001/19/20001/19/2000 12:00:00 AMAPART
dan-- ###-#### ft insp Ftg. 1/19/00 1:39:39 PM
BLD99-03379 BLD-Other1/18/20001/19/20001/19/2000 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 01/18/2000 at 15:58:27. Contact: ###-####. C/N firestops. 1/19/00 1:40:22 PM
BLD99-02513 BLD-Final1/18/20001/19/20001/19/2000 12:00:00 AMAFAIL
sid ###-#### C/N; clearance @ corridor door (12" min). 1/19/00 1:40:12 PM
BLD99-03121 BLD-Framing/Rough-in1/19/20001/19/20001/19/2000 12:00:00 AMAPASS
Check interior shear @ energy.
BLD99-02585 BLD-Framing/Rough-in1/19/20001/19/20001/19/2000 12:00:00 AMAPART
"Shear Insp." nailing ok; C/N: need eng's ok for blocking attachment @ drag strut & extend hold downs.
BLD99-02806 BLD-Conference1/19/20001/19/20001/19/2000 12:00:00 AMAPASS
W/Tim, supt. re: handrail- ok non-continuous @ landing.
BLD99-01410 BLD-Framing/Rough-in1/19/20001/19/20001/19/2000 12:00:00 AMPFAIL
C/N- shaft, handrail, etc.- ok to place ceiling tiles.
BLD99-00682 BLD-Conference1/19/20001/19/20001/19/2000 12:00:00 AMPPASS
BKH's; Rec'd submittal for ceiling (rated) extension @ corridor. ok.
BLD99-03349 BLD-Energy code compliance1/17/20001/19/20001/19/2000 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 01/17/2000 at 13:56:35. Contact: ###-####. Keep C/N; need further info re vault hip roof. 1/20/00 8:57:35 AM
BLD00-00093 BLD-Footing1/19/20001/19/20001/19/2000 12:00:00 AMPPART
###-#### Ftg. 1/20/00 8:57:44 AM
BLD99-03477 BLD-Framing/Rough-in1/19/20001/19/20001/19/2000 12:00:00 AMPPASS
###-#### John Hardy after 3pm Prev. done by 316? 1/20/00 8:57:11 AM
BLD99-01368 BLD-Conference1/19/20001/19/20001/19/2000 12:00:00 AMPPASS
andy-- ###-#### conf-- W/arch. need all ok's for final. 1/20/00 8:58:32 AM
BLD99-03509 BLD-Footing1/19/20001/19/20001/19/2000 12:00:00 AMPPASS
BRuce###-#### Ftg. ok. 1/20/00 8:57:56 AM
BLD99-02745 BLD-Footing1/19/20001/19/20001/19/2000 12:00:00 AMPPART
###-#### Jerry Estep Ext. ftg. @ rear add'n.. no rebar noted on plans. 1/20/00 8:56:56 AM