FIR04-00593
| INSP-Sprinkler Rough-in/Hydro | 1/18/2005 | 1/19/2005 | 1/19/2005 12:00:00 AM | A | PART |
|
|
Kerry-call before you go out; Phone #: ###-#### Internet Inspection Request from: Jan Rice Thrust block on UG okay; overhead okay to cover; will need several cavities filled with insulation as shown on plans; started 24 hr test at 9 am 1/19/2005 3:16:01 PM
|
FIR04-00812
| INSP-Supply line flush | 1/18/2005 | 1/19/2005 | 1/19/2005 12:00:00 AM | A | PART |
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice UG stub out only - okay; used one piece riser 1/19/2005 10:10:01 AM
|
MIS05-00008
| FIR-Final | 1/19/2005 | 1/19/2005 | 1/19/2005 12:00:00 AM | P | PASS |
|
|
|
FIR05-00007
| INSP-Final Inspection | 1/17/2005 | 1/19/2005 | 1/19/2005 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 1/17/2005 at 9:20:20 AM. Contact: ###-####. Per plan review notes concerns: no sidewall heads were used; final okay 1/19/2005 1:57:02 PM
|