Inspections for the day of: Friday, January 19, 2018.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE12-01429 ELE-Aging Inspection1/19/20181/19/20181/19/2018 2:03:14 PM FAIL
Still waiting on contractor.
ELE13-00718 ELE-Aging Inspection1/19/20181/19/20181/19/2018 1:13:05 PM FAIL
Still waiting for contractor to schedule.
ELE18-00120 Conference1/18/20181/19/20181/19/2018 12:50:38 PMADONE
We would like to have a consultation on the lack of grounding in building.
Curtis with ESI is the Superintendent: ###-####
If you can call Larry w/ Enterprise 30 mins prior to site visit: ###-#### Phone #: ###-#### Inspection requested via web by Larry Looney
Discussed existing wiring of Target store. Contact concerned about the absense of equipment grounding conductors in conduits and the use of multi wire branch circuits through out store. EMT conduits are still an approved method for providing equipment grounding system as per 250.118. Multi wire branch circuits at time building was built had been a popular method of wiring. Due to the increase in electronic lighting and equipment multi wire branch circuits are not used as much today because of the possibility of an over load the grounded conductor. As long as installed as per 210.4 multiwire branch circuits are still use today. All existing wiring can remain as is in building as long as violations are not present and new wiring shall be installed to 2017 version of NEC.
ELE17-03142 Final1/18/20181/19/20181/19/2018 11:06:40 AMAPASS
Home owners phone number is ###-#### This is a final for a remodel. Phone #: ###-#### Inspection requested via web by Zane Robertson
Final ok
ELE18-00135 Electrical Rough-In1/18/20181/19/20181/19/2018 10:48:31 AMAFAIL
Contact is Jim Noll Phone #: ###-#### Inspection requested via web by Scott Campbell
Due to change of use building permit required on unfinished room upstairs to north of landing thru 1/2 door. They want to make it a break room. Created MIS and informed receptionist and electrical contractor.
ELE16-03932 Final1/19/20181/19/20181/19/2018 9:57:23 AMAPART
corridor on 5th floor Phone #: ###-#### Inspection requested via web by Cathy Duchek
Area noted signed off in office. Partial final ok
ELE16-03931 Final1/19/20181/19/20181/19/2018 9:56:35 AMAPART
corridor 5th floor, units 401, 402, 404,405,406 Phone #: ###-#### Inspection requested via web by Cathy Duchek
405 bath back splash not in, other areas noted signed off in office. Partial final ok
ELE17-03877 Electrical Rough-In1/19/20181/19/20181/19/2018 8:48:00 AMAPASS
Call Pierce for grid ceiling inspection of 3 northern most bathrooms. Early AM preferred due to event being held in Boise Centre. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo
4 northern bathrooms grid rough in ok cover