BLD01-01780
| BLD-Aging Inspection | 1/2/2002 | 1/2/2002 | 1/2/2002 12:00:00 AM | | PASS |
|
|
|
BLD01-02678
| BLD-Framing/Rough-in | 12/31/2001 | 1/2/2002 | 1/2/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 12/31/2001 at 13:03:32. Contact: ###-####. bouns rm framing/ load pt. at entry. 1/2/2002 4:00:50 PM
|
BLD01-00986
| BLD-Final | 12/31/2001 | 1/2/2002 | 1/2/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/31/2001 at 17:17:45. Contact: ###-####. final ok 1/2/2002 2:32:38 PM
|
BLD01-00986
| BLD-Final | 12/31/2001 | 1/2/2002 | 1/2/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/31/2001 at 17:17:45. Contact: ###-####. final ok 1/2/2002 2:32:38 PM
|
BLD01-02789
| BLD-Energy code compliance | 1/1/2002 | 1/2/2002 | 1/2/2002 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/01/2002 at 19:21:48. Contact: ###-####. c/n idem not completed. 1/2/2002 2:58:25 PM
|
BLD01-01647
| BLD-Framing/Rough-in | 1/2/2002 | 1/2/2002 | 1/2/2002 12:00:00 AM | P | PASS |
|
|
NAIL MIKE ###-#### exterior ok to cover. 1/2/2002 2:25:32 PM
|
BLD01-02678
| BLD-Framing/Rough-in | 1/2/2002 | 1/2/2002 | 1/2/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
BLD01-01725
| BLD-Final | 1/2/2002 | 1/2/2002 | 1/2/2002 12:00:00 AM | P | FAIL |
|
|
###-#### JUSTIN ( KEY IS ABOVE DOOR) fire stop garage/ insulate in floor reinstal. 1/2/2002 3:18:31 PM
|
BLD01-02832
| BLD-Framing/Rough-in | 1/2/2002 | 1/2/2002 | 1/2/2002 12:00:00 AM | P | PART |
|
|
SHEER INSPECTION JUSTIN ###-#### c/n made ok 1/2/2002 3:39:34 PM
|