Inspections for the day of: Wednesday, January 2, 2008.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00898 INSP-Sprinkler Rough-in1/2/20081/2/20081/2/2008 4:53:50 PMPPASS
The sprinkler piping is ok to cover. However resubmittals are required due to additional heads and piping layouts in both of the remote areas.
FIR07-00981 INSP-Final Inspection1/2/20081/2/20081/2/2008 3:57:58 PMPPASS
Permit finaled. Three doors had to be adjusted while I waited and the batteries were replaced due to cracks in the casing.
FIR06-00011 INSP-Alarm Testing1/2/20081/2/20081/2/2008 3:44:28 PMPFAIL
Todays inspection was for the connection between the new central tower and the north tower on the 2nd, 3rd, 4th and 5th floors. See the city approved plans for my deficiency notes
BLD05-00633 FIRE-Final Inspection1/2/20081/2/20081/2/2008 3:41:10 PMPFAIL
The inspection was for the life safety on the 8th and 9th floors. The inspection was stopped on the eighth floor due to exit sign locations not matching the city approved plans. Also one exit sign was not working. Tom directed the electrician to install per the plans and per the installation on the 4th and 5th floors.
FIR07-00996 INSP-Final Inspection12/31/20071/2/20081/2/2008 12:37:22 PMAPASS
Permit finaled
BLD07-02672 FIRE-Final Inspection12/31/20071/2/20081/2/2008 12:37:00 PMAPASS
Life safety passed
FIR07-00945 INSP-Sprinkler Rough-in12/31/20071/2/20081/2/2008 10:00:43 AMAPASS
Sprinkler piping is ok to cover
FIR07-00941 INSP-Final Inspection12/31/20071/2/20081/2/2008 9:00:56 AMAFAIL
Sprinkler piping is ok to cover. Project can not be finaled as requested due to missing ceiling tile.