MEC14-05767
| Pressure Test | 12/31/2014 | 1/2/2015 | 1/2/2015 4:38:43 PM | P | PASS |
|
|
Jared-please call prior to meet Phone #: ###-#### - 20lb gas pass
|
MEC14-04942
| Final | 1/2/2015 | 1/2/2015 | 1/2/2015 3:21:48 PM | P | PASS |
|
|
Can not get answer from homeowner and no number for renter. You can try to call Jeanie on way to see if she will answer ###-####. Thanks Phone #: ###-#### Inspection requested via web by Allie Courter
|
MEC15-00004
| Final | 1/2/2015 | 1/2/2015 | 1/2/2015 2:40:54 PM | P | PASS |
|
|
Please call Robbie @ ###-#### prior to inspection. Thank you. Phone #: ###-#### Inspection requested via web by Rick Borg
|
MEC15-00004
| Pressure Test | 1/2/2015 | 1/2/2015 | 1/2/2015 2:40:40 PM | P | PASS |
|
|
Please call Robbie @ ###-#### prior to inspection. Thank you. Phone #: ###-#### Inspection requested via web by Rick Borg
|
MEC14-05778
| Final | 12/31/2014 | 1/2/2015 | 1/2/2015 1:59:40 PM | P | PASS |
|
|
Call ahead to Eric @ ###-#### to coordinate inspection time. Phone #: ###-#### Inspection requested via web by Angie Maguire
|
MEC14-02170
| Rough-in | 12/31/2014 | 1/2/2015 | 1/2/2015 12:56:22 PM | P | CANC |
|
|
Called Ben. He said nobody is on site and he's not sure this is ready. He said to cancel and he would reschedule
|
MEC15-00001
| Final | 1/2/2015 | 1/2/2015 | 1/2/2015 12:00:41 PM | P | CANC |
|
|
Ready for inspection after 1pm >> Inspection requested via web by MARGIE ROWE Inspection cancelled from web by: MARGIE ROWE
|
MEC14-05702
| Final | 12/31/2014 | 1/2/2015 | 1/2/2015 11:02:19 AM | A | PASS |
|
|
Mechanical Final, please call Ray Humpherys before heading out at ###-#### Phone #: ###-#### Inspection requested via web by TERESA HUTTO
|
MEC15-00005
| Final | 1/2/2015 | 1/2/2015 | 1/2/2015 10:52:27 AM | P | PASS |
|
|
Ready now Eric (installer) is there and be done is 10-15 mins ###-####. Thanks Phone #: ###-#### Inspection requested via web by Allie Courter
|
MEC15-00005
| Pressure Test | 1/2/2015 | 1/2/2015 | 1/2/2015 10:52:08 AM | P | PASS |
|
|
Ready now Eric (installer) is there and be done is 10-15 mins ###-####. Thanks Phone #: ###-#### Inspection requested via web by Allie Courter - 20lb gas pass
|
MEC14-05708
| Conference | 1/2/2015 | 1/2/2015 | 1/2/2015 10:38:25 AM | A | DONE |
|
|
ex Phone #: ###-#### Inspection requested via web by Robin Cox - Discussed routing of exhuast for laundry room on 2nd floor. Noticed that the exhaust fans on the 1st. and 2nd floors are being installed in between the tgi"s, this is a fire rated assembelly and will need fire dampers installed at fire asseembelly penetration. The city plans also show a transfer above door on on 2nd. flioor laundry room. This has a smoke damper on it, It looks like when installed it will also penetrate inside the tgi"s of the laundry room which will require protection of the assembelly where it is penetrated in the ceiling of the laundry room for the grill.
|
MEC14-05766
| Pressure Test | 12/31/2014 | 1/2/2015 | 1/2/2015 8:53:38 AM | A | PASS |
|
|
Dale Phone #: ###-#### - 5lb flue, 20lb gas pass
|
MEC14-05766
| Rough-in | 12/31/2014 | 1/2/2015 | 1/2/2015 8:53:08 AM | A | FAIL |
|
|
Dale Phone #: ###-#### - Need approved acca report on site for rough in, need 1" gap between insulation shield and B-vent for water heater, need to seal floor boots to the floor
|
MEC12-01497
| Mec-Aging Inspection | 1/2/2015 | 1/2/2015 | 1/2/2015 8:39:17 AM | | CANC |
|
|
No calls
|
MEC12-04207
| Mec-Aging Inspection | 1/2/2015 | 1/2/2015 | 1/2/2015 8:39:02 AM | | CANC |
|
|
No calls
|