BLD04-01911
| FIRE-Final Inspection | 1/19/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | A | FAIL |
|
|
I received the layout for the hood appliances but the revised air balance reports still are not approved due to a 458cfm differential 1/20/2005 9:34:55 AM
|
BLD04-02854
| FIRE-Final Inspection | 1/19/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | A | PASS |
|
|
Life safety finaled. Contractor to have correct sticker at main exit for structural. Per A-1 heating the hvac system is a 3 ton unit which is 1200 cfm which won't need the duct smoke detector. 1/20/2005 8:50:56 AM
|
FIR04-00666
| INSP-Sprinkler Rough-in/Hydro | 1/19/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | A | FAIL |
|
|
Insulation is not correct and the branchline running the length of the north corridor does not appear to have any straps on the piping. Provide verification from the structural engineer that it is ok to support the sprinkler piping on the top of the bottom chords of the trusses. This inspection was for the east wing. 1/20/2005 12:02:18 PM
|
FIR05-00005
| INSP-Sprinkler Rough-in | 1/20/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | P | PASS |
|
|
Sprinkler rough-in for the overhead piping and the tenting is ok for cover. Riser is not yet built. Water meter is 1" as shown on plans. 1/20/2005 1:45:39 PM
|
BLD04-02445
| FIRE-Final Inspection | 1/20/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | P | NR |
|
|
darrin -call 1st before insp ; Phone #: ###-#### This building has an alarm system that has not been finaled. The fire alarm contractor has been contacted by me personally about this several times over the past couple of years. I let Darrin know that there would be no inspections until the fire alarm system had been approved. 1/20/2005 3:45:25 PM
|
BLD03-02556
| FIRE-Final Inspection | 1/20/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | P | PASS |
|
|
fire life safety finaled 1/20/2005 2:54:40 PM
|
BLD04-00888
| FIRE-Alarm Testing | 1/20/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | P | CANC |
|
|
KIRT Note: late as possible this AFTERNOON; Phone #: ###-#### Per the contractor the phone lines have not been installed yet. 1/20/2005 3:46:23 PM
|
FIR04-00582
| INSP-Sprinkler Rough-in/Hydro | 1/20/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | P | PART |
|
|
Forward flush was ok. Need to provide valve for lower guage, test papers and certification for the backflow preventer. 1/20/2005 12:06:50 PM
|
BLD04-00838
| FIRE-Conference | 1/20/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | P | DONE |
|
|
Pat; ###-#### I went over life safety requirements with the contractor and owner. 1/20/2005 2:56:05 PM
|
FIR04-00500
| INSP-Final Inspection | 1/20/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | P | PASS |
|
|
Fire alarm system demo'ed
|
BLD04-02804
| FIRE-Final Inspection | 1/19/2005 | 1/20/2005 | 1/20/2005 12:00:00 AM | P | PASS |
|
|
Life safety finaled 1/20/2005 1:48:07 PM
|