Inspections for the day of: Thursday, January 20, 2005.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD04-01911 FIRE-Final Inspection1/19/20051/20/20051/20/2005 12:00:00 AMAFAIL
I received the layout for the hood appliances but the revised air balance reports still are not approved due to a 458cfm differential 1/20/2005 9:34:55 AM
BLD04-02854 FIRE-Final Inspection1/19/20051/20/20051/20/2005 12:00:00 AMAPASS
Life safety finaled. Contractor to have correct sticker at main exit for structural. Per A-1 heating the hvac system is a 3 ton unit which is 1200 cfm which won't need the duct smoke detector. 1/20/2005 8:50:56 AM
FIR04-00666 INSP-Sprinkler Rough-in/Hydro1/19/20051/20/20051/20/2005 12:00:00 AMAFAIL
Insulation is not correct and the branchline running the length of the north corridor does not appear to have any straps on the piping. Provide verification from the structural engineer that it is ok to support the sprinkler piping on the top of the bottom chords of the trusses. This inspection was for the east wing. 1/20/2005 12:02:18 PM
FIR05-00005 INSP-Sprinkler Rough-in1/20/20051/20/20051/20/2005 12:00:00 AMPPASS
Sprinkler rough-in for the overhead piping and the tenting is ok for cover. Riser is not yet built. Water meter is 1" as shown on plans. 1/20/2005 1:45:39 PM
BLD04-02445 FIRE-Final Inspection1/20/20051/20/20051/20/2005 12:00:00 AMPNR
darrin -call 1st before insp ; Phone #: ###-#### This building has an alarm system that has not been finaled. The fire alarm contractor has been contacted by me personally about this several times over the past couple of years. I let Darrin know that there would be no inspections until the fire alarm system had been approved. 1/20/2005 3:45:25 PM
BLD03-02556 FIRE-Final Inspection1/20/20051/20/20051/20/2005 12:00:00 AMPPASS
fire life safety finaled 1/20/2005 2:54:40 PM
BLD04-00888 FIRE-Alarm Testing1/20/20051/20/20051/20/2005 12:00:00 AMPCANC
KIRT Note: late as possible this AFTERNOON; Phone #: ###-#### Per the contractor the phone lines have not been installed yet. 1/20/2005 3:46:23 PM
FIR04-00582 INSP-Sprinkler Rough-in/Hydro1/20/20051/20/20051/20/2005 12:00:00 AMPPART
Forward flush was ok. Need to provide valve for lower guage, test papers and certification for the backflow preventer. 1/20/2005 12:06:50 PM
BLD04-00838 FIRE-Conference1/20/20051/20/20051/20/2005 12:00:00 AMPDONE
Pat; ###-#### I went over life safety requirements with the contractor and owner. 1/20/2005 2:56:05 PM
FIR04-00500 INSP-Final Inspection1/20/20051/20/20051/20/2005 12:00:00 AMPPASS
Fire alarm system demo'ed
BLD04-02804 FIRE-Final Inspection1/19/20051/20/20051/20/2005 12:00:00 AMPPASS
Life safety finaled 1/20/2005 1:48:07 PM