Inspections for the day of: Thursday, January 20, 2011.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR10-00398 INSP-Final Inspection1/20/20111/20/20111/21/2011 1:45:43 PMPPART
Inspection notes 1/20/11- Completed acceptance testing including initiating and notification devices, sprinkler monitoring, and elevator control functions. Verified offsite monitoring. Flashing hat at the elevator is not required due to original installation date of the equipment per plan review. Flow switch at the wet system riser did not pass operational testing. Remainder of items tested okay.
FIR10-00512 INSP-Sprinkler Rough-in1/20/20111/20/20111/20/2011 6:16:29 PMPPART
Provide missing pendent head at the gas room, flow switch did not pass operational test, riser is overdue annual inspection, platform at the roof must meet NFPA 13 2007 sec. 8.15.6.
BLD10-01589 FIRE-Conference1/20/20111/20/20111/20/2011 5:47:23 PMPDONE
On site conference regarding items remaining for fire life safety final approval including fire extinguishers, knox box, EM lights, etc.
FIR10-00631 INSP-Final Inspection1/20/20111/20/20111/20/2011 5:29:51 PMPPASS
Fire alarm reinspection passed. Permit finaled.
FIR10-00425 INSP-Final Inspection1/20/20111/20/20111/20/2011 2:31:04 PMAPASS
Correction items verified for completion. Fire sprinkler permit finaled.
FIR10-00569 INSP-Sprinkler Rough-in/Hydro1/19/20111/20/20111/20/2011 1:07:20 PMAPART
Restrooms okayed for ceiling cover. Noted missing hangers one branch piece per line at the deck, inspectors test connections at the riser to be relocated. Full rough-in inspection not complete.
FIR10-00616 INSP-Final Inspection1/19/20111/20/20111/20/2011 12:50:44 PMAPART
Overhead install okayed with the exception of one lateral seismic brace at the north end 2 1/2" main. Final pending PRV at the riser and main tie-ins.
FIR10-00616 INSP-Sprinkler Rough-in/Hydro1/19/20111/20/20111/20/2011 12:47:29 PMAPART
Overhead hydrostatic testing at the new addition passed.
BLD10-02986 FIRE-Final Inspection1/19/20111/20/20111/20/2011 9:10:24 AMANR
Pending project related building and fire alarm permit finals. NOTE: Project related FIR11-00026 has not yet been reviewed, issued, inspected or approved at this time.