ELE16-01483
| Electrical Rough-In | 1/20/2017 | 1/20/2017 | 1/20/2017 1:37:07 PM | P | PASS |
|
|
We need a rough for the following units, 105, 107, 301. Site contact is Kenny Long. Phone #: ###-#### Inspection requested via web by Stacie Tasker unit 105 hard lid @ units 101, 107 rough-in ok cover
|
ELE16-02600
| Electrical Rough-In | 1/20/2017 | 1/20/2017 | 1/20/2017 12:48:40 PM | P | CANC |
|
|
Matt. Final on 5th Floor. Phone #: ###-#### Inspection requested via web by Sean DeLacy needed temp oc
|
ELE16-02600
| Final | 1/20/2017 | 1/20/2017 | 1/20/2017 12:48:25 PM | P | PART |
|
|
Matt. Final on 5th Floor. Phone #: ###-#### Inspection requested via web by Sean DeLacy All of 5th floor ok will need to check 513 for receptacle to be added in bath
|
ELE17-00129
| Rough-In Permanent Service | 1/20/2017 | 1/20/2017 | 1/20/2017 12:28:36 PM | P | CANC |
|
|
Mother in law quarters in the back Phone #: ###-#### Inspection requested via web by Greg Idsinga Just rough-in at this time
|
ELE17-00129
| Electrical Rough-In | 1/20/2017 | 1/20/2017 | 1/20/2017 12:28:29 PM | P | PASS |
|
|
Mother in law quarters in the back Phone #: ###-#### Inspection requested via web by Greg Idsinga Mother in law quarters ok cover
|
ELE17-00129
| Permanent Service | 1/20/2017 | 1/20/2017 | 1/20/2017 12:28:18 PM | P | FAIL |
|
|
Mother in law quarters in the back Phone #: ###-#### Inspection requested via web by Greg Idsinga 408.36(d) Back fed devices shall be fastened in place(screw missing in main) 230.24 Shall maintain 18' from service drip loop to roof line
|
ELE16-03492
| Final | 1/20/2017 | 1/20/2017 | 1/20/2017 10:41:59 AM | P | PASS |
|
|
Greg Critchfield is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce UPS server room final ok
|
ELE16-02054
| Final | 1/20/2017 | 1/20/2017 | 1/20/2017 10:41:34 AM | P | PASS |
|
|
Greg Critchfield is contact at ###-#### Phone #: ###-#### Inspection requested via web by Debby Pierce Grease interceptor final ok, if more branch circuits pulled out of spare panel a seperate permit required
|
ELE16-01594
| Final | 1/20/2017 | 1/20/2017 | 1/20/2017 10:40:37 AM | P | PASS |
|
|
Greg Critchfield is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce As per Rock Hudson with conference and verifying listing os materials used for 2 hour fire rating and scope of work. Final ok
|
ELE16-02730
| Electrical Rough-In | 1/19/2017 | 1/20/2017 | 1/20/2017 9:39:59 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Bathroom hard lids and walls also and stairways and soffit ok cover
|
ELE17-00132
| Final | 1/19/2017 | 1/20/2017 | 1/20/2017 8:49:11 AM | A | CANC |
|
|
Please contact us for access into the property. Thank you Mayte ###-#### Susan ###-#### Phone #: ###-#### Inspection requested via web by Caliber Home Loans Cannot final until power is energized
|
ELE17-00132
| Permanent Service | 1/20/2017 | 1/20/2017 | 1/20/2017 8:48:59 AM | P | PASS |
|
|
Please contact us for access into the property. Thank you Mayte ###-#### Susan ###-#### Phone #: ###-#### Inspection requested via web by Caliber Home Loans Will call for final after power has been energized p/s u/g rec ok
|