FIR03-00628
| FIR-Aging Inspection | 1/21/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | | NR |
|
|
work in progress 1/21/2004 4:04:10 PM
|
FIR03-00317
| INSP-Conference | 1/21/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | FAIL |
|
|
could not find the sprinkler contractor on site for the conference 1/21/2004 8:55:09 AM
|
FIR03-00647
| INSP-Alarm Testing | 1/21/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | PART |
|
|
The items on he correction notice for the annex (north wing) have been completed. The fire alarm in this area is complete 1/21/2004 8:46:27 AM
|
FIR03-00035
| INSP-Final Inspection | 1/21/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | PASS |
|
|
|
FIR03-00168
| INSP-Final Inspection | 1/21/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | PASS |
|
|
|
FIR03-00206
| INSP-Final Inspection | 1/21/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | PASS |
|
|
|
FIR03-00258
| INSP-Final Inspection | 1/21/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | PASS |
|
|
|
BLD02-02454
| FIRE-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | PASS |
|
|
Fire life safety, fire alarm and fire sprinklers finaled 1/21/2004 11:23:09 AM
|
FIR03-00756
| INSP-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | CANC |
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
FIR03-00812
| INSP-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | CANC |
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
FIR03-00811
| INSP-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | CANC |
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD03-01530
| FIRE-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | CANC |
|
|
rescheduled for tomorrow 1/21/2004 10:26:31 AM
|
FIR03-00450
| INSP-Sprinkler Rough-in/Hydro | 1/20/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | A | PART |
|
|
sprinkler piping is OK to cover 1/21/2004 10:25:30 AM
|
BLD02-02454
| FIRE-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | P | CANC |
|
|
duplicate inspection 1/21/2004 11:24:04 AM
|
FIR03-00505
| INSP-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | P | CANC |
|
|
phone lines not in 1/21/2004 4:05:54 PM
|
FIR03-00448
| INSP-Sprinkler Rough-in | 1/21/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | P | FAIL |
|
|
Inspection was for the rough-in on the attic dry system. Some hangers on the 4" main need to be attached to the top chord of the trusses and two EQ bracings need to be attached to the wall plate. Also need to provide signage showing location of the FDC 1/21/2004 3:03:54 PM
|
BLD03-01530
| FIRE-Final Inspection | 1/21/2004 | 1/21/2004 | 1/21/2004 12:00:00 AM | P | CANC |
|
|
rescheduled for tomorrow 1/21/2004 3:01:36 PM
|
BLD03-02322
| FIRE-Sprinkler Rough-in | 1/20/2004 | 1/21/2004 | 1/20/2004 12:00:00 AM | A | CANC |
|
|
david; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie--cancel needed framing
|
BLD03-02323
| FIRE-Sprinkler Rough-in | 1/20/2004 | 1/21/2004 | 1/20/2004 12:00:00 AM | A | CANC |
|
|
david; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie--cancel needed framing insp
|