ESC13-00193
| General Inspection | 1/21/2014 | 1/21/2014 | 1/21/2014 12:21:05 PM | | PASS |
|
|
No construction acitivity. SWO still in effect. Construction entrance needs to be installed. Jayo is supposed to schedule re-inspection when work will commence. Road was swept and perimeter wattles prevented runoff to the streets.
|
ESC13-00524
| BMP Violation | 1/21/2014 | 1/21/2014 | 1/21/2014 12:10:29 PM | P | PEND |
|
|
RP Bob Berryman called to inform that corrections have been made at Hackberry Ranch from last weeks CN. Follow up inspection.
Corrections were addressed. Areas of rill erosion were filled in and additional berms and wattles were installed. Wattles also repaired at top of road with long slope. SWPPP inspection was also completed.
Bob Berryman reviewed schedule. Sweeping on Bogus will be conducted by end of week. County inspections next week for water lines and stormwater system and neighborhood streets will be swept. Hydroseeding to be completed in first two weeks of February.
No further corrections for now, just need to sweep up and also make landscaping crews do daily cleaning.
|
ESC13-00717
| General Inspection | 1/21/2014 | 1/21/2014 | 1/21/2014 10:43:18 AM | | PASS |
|
|
Permit posted. Construction/demo waste in dumpster. No trackout. No corrections at this time.
|
ESC13-00691
| Aging Inspection | 1/21/2014 | 1/21/2014 | 1/21/2014 10:38:28 AM | | PASS |
|
|
Home remodel is in progress. Permit posted on front door. No trackout or other violations observed.
|
ESC13-00344
| General Inspection | 1/21/2014 | 1/21/2014 | 1/21/2014 10:30:39 AM | | PASS |
|
|
Top of windsong was recently swept. Hillsides endured recent snowmelt with only a few minor areas with sediment runoff to sidewalk. New wattles have been installed in some areas. No corrections at this time.
|
ESC13-00486
| General Inspection | 1/21/2014 | 1/21/2014 | 1/21/2014 10:26:27 AM | | PASS |
|
|
No activity at time of inspection. Wattles installed along downslope perimeter. Yard is not yet landscaped/stabilized. Pool consruction on-going in backyard with seperate permit. No corrections at this time.
|
ESC13-01275
| Site Preparation | 1/21/2014 | 1/21/2014 | 1/21/2014 10:15:36 AM | P | PASS |
|
|
austin Phone #: ###-####
Washout restored as requested for sites on this block. Street sweeping on access alley acceptable. Will need to continue daily housekeeping
|
ESC13-01252
| Site Preparation | 1/21/2014 | 1/21/2014 | 1/21/2014 10:05:18 AM | P | PASS |
|
|
austin Phone #: ###-####
Permit posted. Washout was provided with construction entrance as requested. Will need to keep silt fence installed to contain stockpiles.
|
ESC13-00729
| General Inspection | 1/21/2014 | 1/21/2014 | 1/21/2014 9:58:17 AM | | PASS |
|
|
Pool house is complete and surrounding area has been landscaped. Some plant areas have also been covered with tacifier. No corrections at this time. BLD not yet finaled. Will check for final stabilization
|
ESC13-00613
| Site Preparation | 1/21/2014 | 1/21/2014 | 1/21/2014 9:29:24 AM | P | PASS |
|
|
Permit posted. Neighborhood BMPs in acceptable condition. Approved for excavation.
|
ESC13-00719
| General Inspection | 1/21/2014 | 1/21/2014 | 1/21/2014 9:27:27 AM | | PASS |
|
|
Foundation was laid Fall 2013. Vertical construction is begining to resume. No corrections at this time.
|
ESC12-01014
| General Inspection | 1/21/2014 | 1/21/2014 | 1/21/2014 9:12:26 AM | | PASS |
|
|
Finaled.
|
ESC12-01014
| DOC - Permit Finaled | 1/21/2014 | 1/21/2014 | 1/21/2014 9:12:09 AM | P | PASS |
|
|
House complete and landscaped. BLD permit has been finaled. Multifamily house is now for sale. ESC conditions satisfied.
|
ESC13-00747
| General Inspection | 1/17/2014 | 1/21/2014 | 1/21/2014 8:25:49 AM | A | PASS |
|
|
No corrections at this time. Stockpiles stored in low risk area with barriers to MS4. Construction entrance is satisfactory.
|