Inspections for the day of: Wednesday, January 21, 2015.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRex Boyles
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE15-00063 Electrical Rough-In1/20/20151/21/20151/21/2015 3:14:36 PMPPASS
Inspection for Cover on Walls, 3rd floor of the Key Bank building
Contact Seth VanWassenhove Phone #: ###-#### Inspection requested via web by Tom Betty r/i walls ok
ELE15-00142 Rough-In Permanent Service1/20/20151/21/20151/21/2015 2:18:37 PMPPASS
Phone #: ###-#### Inspection requested via web by Darryn Coburn r/i ok p/s u/g n ok
GCE15-00009 GCE-Final1/21/20151/21/20151/21/2015 12:32:46 PMPPASS
Duane ###-#### final ok
GCE14-00201 GCE-Rough-In1/20/20151/21/20151/21/2015 12:15:09 PMPPASS
Hudson ###-#### light pole bases and underground ok to cover r/i ok
ELE15-00141 Rough-In Permanent Service1/20/20151/21/20151/21/2015 11:41:11 AMAPASS
Phone #: ###-#### Inspection requested via web by PAT MILLER p/s o/h rec ok r/i for panel change out ok
ELE14-03402 Electrical Rough-In1/20/20151/21/20151/21/2015 9:59:27 AMAPASS
underslab approval (green house) Phone #: ###-#### Inspection requested via web by Brandon Winters underslab conduits r/i ok to cover
GCE14-00210 GCE-Final1/20/20151/21/20151/21/2015 9:26:33 AMAPASS
Dennis ###-#### final ok
GCE14-00215 GCE-Final1/20/20151/21/20151/21/2015 8:59:09 AMAPASS
Brandon ###-#### - floor heat insp. final ok
GCE14-00135 GCE-Final1/20/20151/21/20151/21/2015 8:57:00 AMAPASS
Brandon ###-#### final ok
ELE15-02132 Conference1/21/20151/21/20151/21/2015 12:00:00 AMADONE
Discuss panel clearances in units. Phone #: ###-#### Inspection requested via web by Rafael Castillo discuss hvac above loadcenters in each unit. Lea requesting to install nm cable now without roof done.