Inspections for the day of: Thursday, January 21, 2016.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00893 INSP-Sprinkler Rough-in1/21/20161/21/20161/21/2016 1:47:13 PMPPASS
Rough-in passed. Piping can be covered. Plans/as-builts need submitted showing the reduced scope of work.
BLD15-03651 FIRE-Final Inspection1/20/20161/21/20161/21/2016 11:58:37 AMAFAIL
The pendant sprinkler head at the new restroom is overspaced. The maximum spacing for these heads is 130 sq. ft. Also automatic flush bolts are needed for the inactive leaf of the main exit or get with plan review and see if hardware can be deleted.
BLD15-03223 FIRE-Final Inspection1/20/20161/21/20161/21/2016 10:56:45 AMAFAIL
Repair all exit signs and emergency lights and provide testing, provide egress sensors/request to exit buttons on the doors utilizing the mag locks, remove thumbturn dead bolts, contact scott arellano for guidence on the too narrow drive way around the south side of building and the now blocked off fire dept access from the adjoinging parking lot due to the new fence and three manual gates to the property that are not shown on the city approved plans.
FIR15-00894 INSP-Final Inspection1/20/20161/21/20161/21/2016 10:54:03 AMAPASS
Permit finaled
BLD15-04378 FIRE-Final Inspection1/20/20161/21/20161/21/2016 10:53:36 AMAPASS
Life safety passed
BLD15-04337 FIRE-Final Inspection1/20/20161/21/20161/21/2016 10:53:14 AMAPASS
Life safety passed. The locking hardware from the therapy area to the office needs to be removed due to the exit sign over the door. This needs to be changed as discussed prior to a building inspection.