NAF14-00010
| INSP-Sprinkler Rough-in | 1/20/2016 | 1/21/2016 | 1/21/2016 4:22:15 PM | A | NR |
|
|
Tenting was not complete at time of inspection (10:30 am). Was not able to reinspect, inspection needs to be rescheduled.
|
NAF16-00001
| INSP-Final | 1/20/2016 | 1/21/2016 | 1/21/2016 11:34:40 AM | A | PASS |
|
|
Scope of work complete. Permit Finaled
|
GCB15-00028
| FIRE-Final Inspection | 1/20/2016 | 1/21/2016 | 1/21/2016 8:46:24 AM | P | CANC |
|
|
Fire Final already completed on 1/12/16. NAF permit has been finaled. Called Norma ###-#### and discussed that she needs the BLD final instead.
|
GCB15-00121
| FIRE-Conference | 1/21/2016 | 1/21/2016 | 1/21/2016 12:00:00 AM | A | DONE |
|
|
Sprinkler final complete. Verify correct ring installed on hangar at life safety inspection.
|