Inspections for the day of: Thursday, January 21, 2016.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
NAF14-00010 INSP-Sprinkler Rough-in1/20/20161/21/20161/21/2016 4:22:15 PMANR
Tenting was not complete at time of inspection (10:30 am). Was not able to reinspect, inspection needs to be rescheduled.
NAF16-00001 INSP-Final1/20/20161/21/20161/21/2016 11:34:40 AMAPASS
Scope of work complete. Permit Finaled
GCB15-00028 FIRE-Final Inspection1/20/20161/21/20161/21/2016 8:46:24 AMPCANC
Fire Final already completed on 1/12/16. NAF permit has been finaled. Called Norma ###-#### and discussed that she needs the BLD final instead.
GCB15-00121 FIRE-Conference1/21/20161/21/20161/21/2016 12:00:00 AMADONE