Inspections for the day of: Thursday, January 22, 1998.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD97-00401 INSP - Conference1/22/19981/22/19981/22/1998 12:00:00 AMAPASS
W/ DAN STUART RE SUBMITTAL FROM ANDERSON CONST RE 1HR HPM PIPING ENCLOSURE...WILL MEET W/ CONT NEXT WEEK
BLD97-02102 INSP - Conference1/22/19981/22/19981/22/1998 12:00:00 AMAPASS
W/ CONC. CONT.
BLD97-03592 INSP - Framing/Rough-in1/21/19981/22/19981/22/1998 12:00:00 AMAPART
###-#### JACOBSON\ SHE WILL BE HOME FROM 8:00 UNTIL 11:00 OR AFTER 3:30 per ba...SUN ROOM KIT??...NO PLAN, LOOKS OK. COMPLETED?
BLD97-03648 INSP - Energy code compliance1/22/19981/22/19981/22/1998 12:00:00 AMPPASS
PROBLEM MARK ###-####--OWNER WILL BE HOME
BLD97-03648 INSP - Framing/Rough-in1/22/19981/22/19981/22/1998 12:00:00 AMPPASS
reinsp
MEC98-00181 INSP - Framing/ Rough-in1/22/19981/22/19981/22/1998 12:00:00 AMPNR
please pete ###-####...called, left msg, no response...
BLD96-02800 INSP - Conference1/22/19981/22/19981/22/1998 12:00:00 AMPPASS
sent fax letter to Scott at lombard-conrad: detail ok if fasteners detailed
BLD97-02104 INSP - Framing/Rough-in1/22/19981/22/19981/22/1998 12:00:00 AMPNR
waterfront \\###-####....not frame insp, carpentry only
BLD97-02223 INSP - Conference1/23/19981/22/19981/22/1998 12:00:00 AMPPASS
w/ wes re c/n & mech...he wrote struct c/n, owner wants final asap, will need bond.
BLD97-02259 INSP - Carpentry1/22/19981/22/19981/22/1998 12:00:00 AMPPASS
got arch's detail & calcs from Ron Hill
BLD97-02497 INSP - Foundation1/22/19981/22/19981/22/1998 12:00:00 AMPNR
incorrect plan onsite
BLD97-03197 INSP - Carpentry1/22/19981/22/19981/22/1997 12:00:00 AMPPART
has incorrect eng's letter, need prior to pour. ok to begin perimeter ftgs,. need detail for pads w/ imbeds for steel frame; told to have builder call me.