MEC01-02408
| MEC-Aging Inspection | 1/22/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | | PASS |
|
|
finaled by 316 1/22/2002 12:07:27 PM
|
MEC01-03163
| MEC-Aging Inspection | 1/22/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | | PASS |
|
|
WORK IN PROGRESS 1/22/2002 6:37:57 PM
|
MEC02-00141
| Final | 1/16/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/16/2002 at 14:05:04. Contact: ###-####. condensate not per manufactures..called chris 1/22/2002 10:56:04 AM
|
MEC01-03770
| Rough-in | 1/18/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/18/2002 at 13:55:20. Contact: .
|
MEC01-02428
| Final | 1/18/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/18/2002 at 15:09:27. Contact: ###-####.
|
MEC02-00102
| Pressure Test | 1/18/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/18/2002 at 15:16:08. Contact: ###-####.
|
MEC02-00102
| Rough-in | 1/18/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/18/2002 at 15:16:16. Contact: ###-####. not even ready for a r/i yet 1/22/2002 11:47:00 AM
|
MEC02-00171
| Pressure Test | 1/21/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/21/2002 at 12:04:59. Contact: ###-####.
|
MEC01-03286
| Final | 1/21/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/21/2002 at 08:32:22. Contact: ###-####. no unions allowed in basement gas pipe...no access to furnace in crawl...to deep to jump 1/22/2002 5:19:19 PM
|
MEC02-00179
| Final | 1/22/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/22/2002 at 09:11:22. Contact: ###-####.
|
MEC02-00183
| Rough-in | 1/22/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/22/2002 at 09:59:04. Contact: ###-####.
|
MEC02-00183
| Pressure Test | 1/22/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/22/2002 at 09:59:25. Contact: ###-####.
|
MEC02-00189
| Rough-in | 1/22/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | P | FAIL |
|
|
tony ###-#### r/i posted corrections..gas leaking also 1/22/2002 5:19:42 PM
|
MEC01-03552
| Final | 1/22/2002 | 1/22/2002 | 1/22/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/22/2002 at 10:52:20. Contact: ###-####.
|