Inspections for the day of: Thursday, January 22, 2009.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Strole
TitlePLM/MEC-INSPECTOR
Phone #794-7913
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM08-02630 Final1/22/20091/22/20091/22/2009 4:14:44 PMPPASS
BOB Phone #: ###-####
PLM08-01792 Plumbing Rough-in1/22/20091/22/20091/22/2009 3:45:17 PMPPART
PARTIAL ROUGH-IN. PLEASE SCHEDULE AROUND 3:30. CALL JAY BROWN AT ###-#### IF YOU HAVE ANY QUESTIONS. Phone #: ###-#### Internet Inspection Request from: Ann Marie Reyes-ok to 1 side all walls except main mens & womens bath. need roof drains complete & tested & inspection on main baths.
PLM09-00085 Plumbing Rough-in1/22/20091/22/20091/22/2009 2:36:39 PMPPASS
jeff Phone #: ###-####-rough-in pass, need tie in of building drain & water.
PLM09-00074 Final1/22/20091/22/20091/22/2009 1:47:27 PMPPASS
dave Phone #: ###-####
ESC08-00539 Tracking Control1/21/20091/22/20091/22/2009 1:36:17 PMPPART
talked with rp about cleaning up tracking on a daily basis due to the amount of traffic on & off project. clint smith will reinspect monday 1-25-09
PLM08-02581 Final1/21/20091/22/20091/22/2009 10:15:32 AMAPASS
bryan Phone #: ###-####
PLM08-01432 Final1/21/20091/22/20091/22/2009 10:15:09 AMAPASS
bryan Phone #: ###-####