MEC19-05773
| Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 4:08:53 PM | P | NH |
|
|
Please inspect later PM. Val in on site ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks - no access to project
|
MEC19-05773
| Final | 1/21/2020 | 1/22/2020 | 1/22/2020 4:08:12 PM | P | CANC |
|
|
Please inspect later PM. Val in on site ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks - no access project on backside of house boarded up and no answer at front door
|
MEC20-00301
| Final | 1/21/2020 | 1/22/2020 | 1/22/2020 4:07:12 PM | P | PASS |
|
|
Please inspect later PM call chuck on your way - ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks - furnace ac coil co ok
|
MEC20-00298
| Final | 1/22/2020 | 1/22/2020 | 1/22/2020 2:32:19 PM | P | PASS |
|
|
Please call Janet Phillips prior to arrival. ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette - furnace only co ok
|
PLM20-00060
| Water Heater Final | 1/22/2020 | 1/22/2020 | 1/22/2020 2:15:17 PM | P | FAIL |
|
|
- t&p needs ran in new materials to 6-24" above floor and should not have weep hole in material
|
MEC19-05758
| Rough-in | 1/22/2020 | 1/22/2020 | 1/22/2020 2:10:57 PM | P | NR |
|
|
Christian ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks - not ready - exhaust fan still not hooked up - range vent will need to be sealed by final ok project
|
MEC20-00264
| Rough-in | 1/20/2020 | 1/22/2020 | 1/22/2020 11:23:16 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Randy Hart - need approved Man J onsite
|
MEC20-00264
| Pressure Test | 1/20/2020 | 1/22/2020 | 1/22/2020 11:22:54 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Randy Hart - 5lb flue pressure test ok - 20lb gas pressure test ok - tagged meter location
|
MEC19-04659
| Final | 1/20/2020 | 1/22/2020 | 1/22/2020 11:19:35 AM | A | PASS |
|
|
2468 Phone #: ###-#### Inspection requested via web by Randy Hart - final ok
|
MEC20-00263
| Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 11:19:16 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Randy Hart -R/I ok
|
MEC20-00166
| Final | 1/15/2020 | 1/22/2020 | 1/22/2020 10:55:42 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette - furnace ac coil co ok
|
MEC19-04655
| Final | 1/16/2020 | 1/22/2020 | 1/22/2020 10:40:12 AM | A | PASS |
|
|
Inspection requested via web by Denise Colin - final ok
|
MEC19-04655
| Pressure Test | 1/16/2020 | 1/22/2020 | 1/22/2020 10:38:55 AM | A | PASS |
|
|
Inspection requested via web by Denise Colin - 5lb flue pressure test ok
|
MEC20-00017
| Final | 1/20/2020 | 1/22/2020 | 1/22/2020 9:53:56 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette - furnace ac coil co ok
|
MEC20-00271
| Final | 1/20/2020 | 1/22/2020 | 1/22/2020 9:37:51 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette - air handler only ok
|
MEC20-00236
| Pressure Test | 1/22/2020 | 1/22/2020 | 1/22/2020 9:17:39 AM | A | FAIL |
|
|
installer John ###-#### (yesterday) project manager Dennis ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt - 20lb gas pressure test ok - need to see electrical permit issued for generator for pass on pressure test and final
|
MEC20-00210
| Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 9:01:44 AM | A | PASS |
|
|
Inspection requested via web by Sheldon Lebow - fireplace R/I - need CSST sleeved with PVC through equipment per specs by final
|
MEC20-00210
| Pressure Test | 1/15/2020 | 1/22/2020 | 1/22/2020 8:54:36 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Sheldon Lebow - 20lb gas pressure test ok
|
MEC19-04758
| Final | 1/22/2020 | 1/22/2020 | 1/22/2020 8:35:23 AM | A | PART |
|
|
Temp final ok on area A units only 103,104,105,106, lobby 203, 204, 205, 302 and parking garage - Fireplaces in Area B still need to have final inspection done
|
MEC19-02877
| Mec-Aging Inspection | 1/22/2020 | 1/22/2020 | 1/22/2020 8:00:17 AM | | FAIL |
|
|
Schedule inspection with homeowner once corrections have been made. Permit failed inspection on 10-9-19 and hasn't been active since.
|
MEC18-03013
| Mec-Aging Inspection | 1/22/2020 | 1/22/2020 | 1/22/2020 7:58:39 AM | | DONE |
|
|
Permit was just re opened on 1-21-20 after being expired. Schedule inspection when work is finished.
|
MEC19-01280
| Mec-Aging Inspection | 1/22/2020 | 1/22/2020 | 1/22/2020 7:56:20 AM | | DONE |
|
|
WIP
|
MEC20-00210
| Rough-in | 1/15/2020 | 1/22/2020 | 1/21/2020 9:51:13 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Sheldon Lebow Inspection cancelled from web by: Sheldon Lebow
|