Inspections for the day of: Thursday, January 23, 2003.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-00228 BLD-Aging Inspection1/23/20031/23/20031/29/2003 12:00:00 AM PASS
spoke w/ St Lukes...stilll awaiting eng's clarification/ok re seismic upgrade (original project)...new supt advised. 1/29/2003 9:20:44 AM
BLD01-00299 BLD-Aging Inspection1/23/20031/23/20031/23/2003 12:00:00 AM PART
grading only, ok 1/23/2003 9:45:45 AM
BLD01-01377 BLD-Framing/Rough-in1/22/20031/23/20031/23/2003 12:00:00 AMACANC
###-####
BLD00-03729 BLD-Framing/Rough-in1/22/20031/23/20031/23/2003 12:00:00 AMACANC
CEILING GRID--BRUCE; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD02-02379 BLD-Framing/Rough-in1/22/20031/23/20031/23/2003 12:00:00 AMANR
gary ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
MEC02-02984 Rough-in1/22/20031/23/20031/23/2003 12:00:00 AMANR
Scheduled by a contractor via Hello! on 01/22/2003 at 14:42:07. Contact: .
BLD02-02443 BLD-Final1/22/20031/23/20031/23/2003 12:00:00 AMAPASS
###-####...ok , pend P&Z...1/23/2003 10:18:16 AM 1/23/2003 10:19:14 AM
BLD02-01930 BLD-Final1/22/20031/23/20031/23/2003 12:00:00 AMAPASS
###-####
BLD02-01928 BLD-Final1/22/20031/23/20031/23/2003 12:00:00 AMAPASS
###-####
BLD02-00199 BLD-Conference1/23/20031/23/20031/23/2003 12:00:00 AMAPASS
see BLD02-00163 history, too. 1/23/2003 10:50:04 AM
BLD02-00163 BLD-Conference1/23/20031/23/20031/23/2003 12:00:00 AMAPASS
met onsite w/ Brian, Mcalvaine supt. & GS....foundation work is generally per the plans...work has proceeded to North/South Bulkheads....decking is just beginning. Advised Mcalvaine that substantial change (stopping project at bulkhead?...demarcation to "Water Center" foundation...) will require resubmittal & review. Add'l (civil/drainage) plans were to be resubmitted by Chad w/ B&A eng'g, informed Marlene he'd have to have review by Pub Wks. & Plbg...& letter assuming eng's duties.
BLD02-00163 BLD-Conference1/23/20031/23/20031/23/2003 12:00:00 AMPCANC
BLD01-01377 BLD-Framing/Rough-in1/23/20031/23/20031/23/2003 12:00:00 AMPPART
charlie ...arch's detail onsite to "tunnel corridor; seal bulkeads to elev. lobby at bsmt, phase 1 of project. 1/23/2003 3:03:39 PM
BLD00-03729 BLD-Framing/Rough-in1/23/20031/23/20031/23/2003 12:00:00 AMPPART
Grid bsmt.& main fl...add spreaders w/ tiles as needed. 1/23/2003 3:39:47 PM
BLD02-00057 BLD-Conference1/23/20031/23/20031/23/2003 12:00:00 AMPPASS
eng'r ok'd seismic upgrade ...wip 1/23/2003 2:26:16 PM
BLD02-00045 BLD-Conference1/23/20031/23/20031/23/2003 12:00:00 AMPCANC
BLD02-00345 BLD-Conference1/23/20031/23/20031/23/2003 12:00:00 AMPPASS
rec'd eng's ok re spec insp items 1/23/2003 2:25:40 PM
BLD02-01202 BLD-Conference1/23/20031/23/20031/23/2003 12:00:00 AMPPASS
final approved 1/23/2003 1:38:06 PM
BLD00-03729 BLD-Framing/Rough-in1/23/20031/23/20031/23/2003 12:00:00 AMPPART
rms 144,145,146, 148, 149. ok...hard lids 217, 218 ok.
MEC02-02984 Rough-in1/23/20031/23/20031/23/2003 12:00:00 AMPPASS
c/n ok..
BLD02-02379 BLD-Framing/Rough-in1/23/20031/23/20031/23/2003 12:00:00 AMPPART
keep c/n...chk w/ insul. 1/23/2003 3:57:04 PM
MEC02-02984 Conference1/23/20031/23/20031/23/2003 12:00:00 AMPPASS
re c/n... add backing for 1hr lid at garage 1/24/2003 8:14:18 AM