FIR05-00712
| INSP-Final Inspection | 1/20/2006 | 1/23/2006 | 1/23/2006 4:20:30 PM | A | FAIL |
|
|
Tested areas on first floor phase 1 today, flow switch on sprinkler riser non-functional, restroom a/v is non-functional, provide signage on FACP room door, provide lock at circut breaker, strobes are not in synchronization within the HC rooms-provide door closures or sync mod., strobes in a portion of the corridor are not in sync, insufficient visual coverage in the kitchen, elevator not tested at this time.
|
FIR05-00631
| INSP-Sprinkler Rough-in/Hydro | 1/20/2006 | 1/23/2006 | 1/23/2006 11:06:28 AM | A | PART |
|
|
Two areas as noted lack proper tenting, one head in the sauna room is not installed at this time, two heads have been added below the stairs adjacent to the riser, riser not complete, discussed coverage of the heating unit for the sauna, overhead rough-in is acceptable for cover as noted.
|
FIR04-00490
| INSP-Sprinkler Rough-in/Hydro | 1/23/2006 | 1/23/2006 | | A | |
|
|
Check for completion.
|