BLD16-03671
| FIRE-Conference | 1/24/2017 | 1/25/2017 | 1/25/2017 2:53:50 PM | A | DONE |
|
|
Randy Phone #: ###-####
|
FIR16-00223
| INSP-Sprinkler Rough-in | 1/24/2017 | 1/25/2017 | 1/25/2017 1:17:48 PM | A | DONE |
|
|
24 hr test started at 1:00pm with 45psi on the guage.
I also spoke to the general contractor about the requirements for a sloped floor and floor drain in the fire pump room.
|
FIR16-00664
| INSP-Sprinkler Rough-in | 1/24/2017 | 1/25/2017 | 1/25/2017 11:55:15 AM | A | PASS |
|
|
Tenting Inspection passed. Piping can be covered.
|
BLD16-04330
| FIRE-Final Inspection | 1/23/2017 | 1/25/2017 | 1/25/2017 11:23:48 AM | A | FAIL |
|
|
Need city approved plans/small documents, need verification of fire alarm monitoring, will probably need ada hardware on door the separates office from the warehouse, overspaced sprinkler pendants in the office will need modified and require a permit for the work.
|
BLD16-04046
| FIRE-Final Inspection | 1/24/2017 | 1/25/2017 | 1/25/2017 10:09:55 AM | A | FAIL |
|
|
Provide address facing the street as discussed, repair the three exit sign/emergency lights as marked on the plans, discuss with plan review the barrier and lack of egress from the east end of the storage ared due to a barrier built that is not shown on the plans.
|
BLD16-03903
| FIRE-Final Inspection | 1/24/2017 | 1/25/2017 | 1/25/2017 10:07:53 AM | A | FAIL |
|
|
Called contact repeatedly starting at 9:00am and kept getting busy signals. Arrived at project 20 minutes later but made no contact. No inspection performed. Larry Phone #: ###-####
|
BLD16-03902
| FIRE-Final Inspection | 1/24/2017 | 1/25/2017 | 1/25/2017 10:07:37 AM | A | FAIL |
|
|
Called contact repeatedly starting at 9:00am and kept getting busy signals. Arrived at project 20 minutes later but made no contact. No inspection performed. Larry Phone #: ###-####
|