BLD00-03303
| BLD-Final | 1/24/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | A | PASS |
|
|
mike ###-#### you went to the wrong one and finaled the wrong permit number
|
BLD00-02809
| BLD-Footing | 1/25/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | A | PASS |
|
|
ft insp tim ###-####
|
BLD00-03232
| BLD-Final | 1/25/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/25/2001 at 11:59:27. Contact: ###-####.
|
BLD00-03304
| BLD-Final | 1/24/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | A | PASS |
|
|
mike ###-####
|
BLD00-03645
| BLD-Framing/Rough-in | 1/26/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 407 On 1/26/2001 12:15:26 PM partial inspection of the planed 3 phase interior,left east side at this time,no approved plans on site will recall for inspection on 1/29/01.
|
BLD00-03297
| BLD-Final | 1/24/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | P | PASS |
|
|
mike ###-####
|
BLD00-03434
| BLD-Final | 1/25/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 01/25/2001 at 17:50:54. Contact: ###-####.needs plumbing insp , door closers removed from restrooms also 2 braces at top of left hall walls c/n posted. 1/26/2001 2:25:39 PM
|
BLD01-00076
| BLD-Footing | 1/26/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | P | PASS |
|
|
jed ###-####
|
BLD00-03307
| BLD-Footing | 1/26/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | P | PART |
|
|
Jed ###-####
|
BLD00-03211
| BLD-Final | 1/26/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 01/26/2001 at 08:35:07. Contact: ###-####.ok for temp oc c/n posted,bathroom floor hard surf req 5 in up. 1/26/2001 2:07:57 PM
|
BLD00-03364
| BLD-Final | 1/26/2001 | 1/26/2001 | 1/26/2001 12:00:00 AM | P | PASS |
|
|
|