FIR09-00549
| INSP-Final Inspection | 1/25/2010 | 1/26/2010 | 1/26/2010 3:59:51 PM | P | FAIL |
|
|
The NetCon reading for the AES panel was only 6 so no testing was performed. I did a conference/walk through with Guy and found two strobes in the north and south corridors to be overspaced but if the candellas are raised they will meet code for room spacing requirements. Also a 110cd strobe in the Handi-cap room is located too close to the ceiling. It will need to be changed to a 177cd or be lowered be 24" or more from the ceilign as per NFPA 72 sleeping area visula requirements. The manual pull station in the fire sprinkler riser room was mounted too high but Guy lowered it while I was on site. The location of all of the other a/v's were veriified and appear ok.
|
FIR09-00448
| INSP-Final Inspection | 1/26/2010 | 1/26/2010 | 1/26/2010 3:47:43 PM | P | FAIL |
|
|
Once the fire alarm interconnects have been tested this permit can be finaled. The forward flush test passed. I notified the building contractor that the fire sprinkler riser room does not meet the one hour rating requirement per boise city ordinance.
|