FIR14-00541
| INSP-Sprinkler Rough-in/Hydro | 1/22/2015 | 1/26/2015 | 1/26/2015 3:44:34 PM | P | FAIL |
|
|
Overhead hydro test failed.
|
FIR14-00540
| INSP-Sprinkler Rough-in/Hydro | 1/22/2015 | 1/26/2015 | 1/26/2015 2:59:17 PM | P | PASS |
|
|
Overhead hydro test passed.
|
FIR15-00017
| INSP-Sprinkler Rough-in | 1/26/2015 | 1/26/2015 | 1/26/2015 2:47:48 PM | P | PASS |
|
|
Rough-in passed. Piping can be covered.
|
BLD14-00948
| FIRE-Conference | 1/26/2015 | 1/26/2015 | 1/26/2015 1:37:32 PM | P | DONE |
|
|
Mike and I discussed life safety requirements and phasing of the project.
|
BLD14-03618
| FIRE-Conference | 1/26/2015 | 1/26/2015 | 1/26/2015 1:37:01 PM | P | DONE |
|
|
Matt discussed life safety requirements. It appears exit signs/ermergency lights need repaired and fire extinguishers tagged
|
BLD14-03617
| FIRE-Conference | 1/23/2015 | 1/26/2015 | 1/26/2015 1:35:54 PM | A | DONE |
|
|
Matt and I discussed life safety requirements. I deferred him to the plan reviewer for interior door hardware requirements and possible emergency lighting requirements.
|