BLD15-04290
| FIRE-Final Inspection | 1/26/2016 | 1/26/2016 | 1/26/2016 2:47:18 PM | P | PASS |
|
|
No fire sprinklers, no fire alarms. Life fire safety passed/complete.
|
BLD15-04396
| FIRE-Final Inspection | 1/25/2016 | 1/26/2016 | 1/26/2016 12:38:32 PM | P | PASS |
|
|
No fire sprinklers, no fire alarms, fire extinguishers are current. Life fire safety inspection passed/complete.
|
BLD15-04376
| FIRE-Final Inspection | 1/25/2016 | 1/26/2016 | 1/26/2016 12:37:34 PM | P | PASS |
|
|
No fire sprinklers, no fire alarms, fire extinguishers are current. Life fire safety inspection passed/complete.
|
BLD15-01841
| FIRE-Final Inspection | 1/26/2016 | 1/26/2016 | 1/26/2016 12:20:29 PM | P | PASS |
|
|
No fire sprinklers, no fire alarms. Core and shell life fire safety passed/complete.
|
BLD15-01841
| FIRE-Sprinkler Rough-in | 1/26/2016 | 1/26/2016 | 1/26/2016 12:18:36 PM | P | CANC |
|
|
Inspection request not for fire sprinkler rough in, inspection request suppose to be final for life fire safety, canceling this inspection request and generating a new one.
|
FIR15-00796
| INSP-Sprinkler Rough-in/Hydro | 1/26/2016 | 1/26/2016 | 1/26/2016 11:42:34 AM | P | PART |
|
|
2 hour hydrostatic test @ 200psi complete for overhead sprinkler piping. Rough to cover inspection complete for building 4, 1st level approved for cover, 2nd level needs tenting installed over piping in attic space, can not cover 2nd level until tenting is inspected.
|