FIR06-00901
| FIR-Aging Inspection | 1/27/2009 | 1/27/2009 | 1/28/2009 5:46:51 PM | P | DONE |
|
|
Confirm state elevator inspection.
|
FIR07-00928
| INSP-Sprinkler Rough-in/Hydro | 1/26/2009 | 1/27/2009 | 1/27/2009 4:18:38 PM | P | PART |
|
|
Fire pump acceptance testing including rated and 150% flow tests and rooftop flow test completed acceptable.
|
FIR08-00766
| INSP-Sprinkler Rough-in | 1/27/2009 | 1/27/2009 | 1/27/2009 4:15:48 PM | P | PART |
|
|
UG fire supply pipe per red-line annotations with todays date on approved plan set okayed for bury, (NE corner).
|
FIR08-00165
| INSP-Final Inspection | 1/27/2009 | 1/27/2009 | 1/27/2009 3:33:40 PM | P | PASS |
|
|
Fire sprinkler permit finaled.
|
FIR08-00165
| FIR-Aging Inspection | 1/27/2009 | 1/27/2009 | 1/27/2009 3:33:11 PM | P | DONE |
|
|
fpp permit open for first floor test kichen. 301 Okay for final. 410
|
FIR07-01005
| FIR-Aging Inspection | 1/27/2009 | 1/27/2009 | 1/27/2009 3:30:02 PM | P | DONE |
|
|
Fire sprinkler permit finaled.
|
FIR08-00461
| INSP-Sprinkler Rough-in/Hydro | 1/23/2009 | 1/27/2009 | 1/27/2009 12:57:40 PM | A | PART |
|
|
OH sprinkler piping and drops okayed for ceiling cover at the 7th floor common corridor, noted one missing hanger at an armover to be installed today, discussed sw head locations at the cable closets adjacent to the elevator hoistway.
|
BLD09-00045
| FIRE-Final Inspection | 1/26/2009 | 1/27/2009 | 1/27/2009 12:54:30 PM | A | PASS |
|
|
Life safety inspection passed.
|
FIR08-00641
| INSP-Sprinkler Rough-in | 1/26/2009 | 1/27/2009 | 1/27/2009 12:04:01 PM | A | PART |
|
|
OH fire sprinkler system modifications are okay for ceiling cover, noted some heads will need to be replaced due to paint/texture overspray-see annotations on plans.
|
FIR08-00724
| FIR-Aging Inspection | 1/27/2009 | 1/27/2009 | 1/27/2009 11:26:47 AM | | DONE |
|
|
WIP, pending site inspection request.
|