Inspections for the day of: Friday, January 28, 2000.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRuss Owen
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-03395 BLD-Framing/Rough-in1/27/20001/28/20001/28/2000 12:00:00 AMAFAIL
gary ###-#### c\n posted 1/31/00 1:20:52 PM
BLD99-01838 BLD-Framing/Rough-in1/27/20001/28/20001/28/2000 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 01/27/2000 at 11:57:57. Contact: ###-####. c\n posted 1/28/00 1:12:22 PM
BLD99-01841 BLD-Framing/Rough-in1/27/20001/28/20001/28/2000 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 01/27/2000 at 11:59:26. Contact: ###-####. c\n posted 1/28/00 1:12:15 PM
BLD99-01840 BLD-Framing/Rough-in1/27/20001/28/20001/28/2000 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 01/27/2000 at 12:00:59. Contact: ###-####. c\n posted 1/28/00 1:11:39 PM
BLD99-03698 BLD-Footing1/27/20001/28/20001/28/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 01/27/2000 at 13:25:58. Contact: ###-####. poured as I was not able to get there in time appears ok 1/31/00 1:20:30 PM
BLD99-03723 BLD-Foundation1/27/20001/28/20001/28/2000 12:00:00 AMAPART
Dane ###-#### poured before i could make it appears ok 1/31/00 1:21:17 PM
BLD00-00092 BLD-Foundation1/27/20001/28/20001/28/2000 12:00:00 AMPNR
REBAR INSP --MONA ###-#### nothing at site no people 1/31/00 1:09:37 PM
BLD99-03468 BLD-Framing/Rough-in1/27/20001/28/20001/28/2000 12:00:00 AMPPASS
sheer panel ###-#### Matt please call him before you go out
BLD99-02757 BLD-Energy code compliance1/28/20001/28/20001/28/2000 12:00:00 AMPFAIL
Also need mech. reinsp. ###-####; Brian. c\n posted 1/31/00 1:10:43 PM
BLD00-00055 BLD-Foundation1/28/20001/28/20001/28/2000 12:00:00 AMPPASS
found wall ---chris ###-#### 2# 4 bars in all walls 1/31/00 1:09:10 PM
BLD00-00059 BLD-Foundation1/28/20001/28/20001/28/2000 12:00:00 AMPPART
Wall insp. Pull @ 3:30. Logan- ###-####. 1/2 poured appears ok 1/31/00 1:10:21 PM
BLD99-03591 BLD-Framing/Rough-in1/28/20001/28/20001/28/2000 12:00:00 AMPPASS
dwayne ###-#### fr insp -re-insp energy code also 1/31/00 1:08:00 PM
BLD99-03633 BLD-Framing/Rough-in1/28/20001/28/20001/28/2000 12:00:00 AMPNR
shear wall mike ###-#### per contractor 1/31/00 1:10:00 PM
BLD00-00010 BLD-Foundation1/28/20001/28/20001/28/2000 12:00:00 AMPPASS
found wall-- jack -###-####
BLD00-00009 BLD-Footing1/28/20001/28/20001/28/2000 12:00:00 AMPPASS
jack ###-#### ft insp
BLD99-02589 BLD-Final1/28/20001/28/20001/28/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 01/28/2000 at 11:00:33. Contact: .