BLD99-03395
| BLD-Framing/Rough-in | 1/27/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | A | FAIL |
|
|
gary ###-#### c\n posted 1/31/00 1:20:52 PM
|
BLD99-01838
| BLD-Framing/Rough-in | 1/27/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/27/2000 at 11:57:57. Contact: ###-####. c\n posted 1/28/00 1:12:22 PM
|
BLD99-01841
| BLD-Framing/Rough-in | 1/27/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/27/2000 at 11:59:26. Contact: ###-####. c\n posted 1/28/00 1:12:15 PM
|
BLD99-01840
| BLD-Framing/Rough-in | 1/27/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/27/2000 at 12:00:59. Contact: ###-####. c\n posted 1/28/00 1:11:39 PM
|
BLD99-03698
| BLD-Footing | 1/27/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 01/27/2000 at 13:25:58. Contact: ###-####. poured as I was not able to get there in time appears ok 1/31/00 1:20:30 PM
|
BLD99-03723
| BLD-Foundation | 1/27/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | A | PART |
|
|
Dane ###-#### poured before i could make it appears ok 1/31/00 1:21:17 PM
|
BLD00-00092
| BLD-Foundation | 1/27/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | NR |
|
|
REBAR INSP --MONA ###-#### nothing at site no people 1/31/00 1:09:37 PM
|
BLD99-03468
| BLD-Framing/Rough-in | 1/27/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | PASS |
|
|
sheer panel ###-#### Matt please call him before you go out
|
BLD99-02757
| BLD-Energy code compliance | 1/28/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | FAIL |
|
|
Also need mech. reinsp. ###-####; Brian. c\n posted 1/31/00 1:10:43 PM
|
BLD00-00055
| BLD-Foundation | 1/28/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | PASS |
|
|
found wall ---chris ###-#### 2# 4 bars in all walls 1/31/00 1:09:10 PM
|
BLD00-00059
| BLD-Foundation | 1/28/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | PART |
|
|
Wall insp. Pull @ 3:30. Logan- ###-####. 1/2 poured appears ok 1/31/00 1:10:21 PM
|
BLD99-03591
| BLD-Framing/Rough-in | 1/28/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | PASS |
|
|
dwayne ###-#### fr insp -re-insp energy code also 1/31/00 1:08:00 PM
|
BLD99-03633
| BLD-Framing/Rough-in | 1/28/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | NR |
|
|
shear wall mike ###-#### per contractor 1/31/00 1:10:00 PM
|
BLD00-00010
| BLD-Foundation | 1/28/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | PASS |
|
|
found wall-- jack -###-####
|
BLD00-00009
| BLD-Footing | 1/28/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | PASS |
|
|
jack ###-#### ft insp
|
BLD99-02589
| BLD-Final | 1/28/2000 | 1/28/2000 | 1/28/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/28/2000 at 11:00:33. Contact: .
|