ELE04-00221
| Temporary Service | 1/27/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | A | PASS |
|
|
###-#### rick
t/s u/g n ok 1/28/2004 9:40:08 AM
|
ELE03-00588
| Final | 1/27/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 1/27/2004 at 11:59:37 AM. ok final 1/28/2004 10:36:14 AM
|
ELE04-00228
| Electrical Rough-In | 1/27/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | A | FAIL |
|
|
###-#### Clyde not ready they to open ceiling to see the work that was done 1/28/2004 8:22:11 AM
|
ELE04-00165
| Final | 1/28/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 1/28/2004 at 6:55:11 AM. Contact: ###-####. needs gfci outlets by a.c. unit need to find listing & lable for air handler units 1/28/2004 9:26:48 AM
|
ELE03-00650
| Electrical Rough-In | 1/28/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | P | CANC |
|
|
JESSE ###-#### wrong type inspection 1/28/2004 4:45:33 PM
|
ELE03-00651
| Final | 1/28/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | P | PASS |
|
|
###-#### JESSE ok part final 5th floor rms 1/28/2004 4:47:19 PM
|
ELE03-00653
| Final | 1/28/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | P | PASS |
|
|
###-#### JESSE ok part final 5th floor rms 1/28/2004 4:46:57 PM
|
ELE03-00654
| Final | 1/28/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | P | PASS |
|
|
###-#### JESSE ok part final 5th floor rms 1/28/2004 4:46:33 PM
|
ELE03-00656
| Final | 1/28/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | P | PASS |
|
|
###-#### JESSE ok part final rms 5th floor 1/28/2004 4:46:12 PM
|
ELE03-00657
| Final | 1/28/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | P | PASS |
|
|
###-#### JESSE ok part final rms 5th floor 1/28/2004 4:47:39 PM
|
ELE03-00650
| Final | 1/28/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | P | PASS |
|
|
ok part final rms 5th floor
|
ELE03-02771
| Electrical Rough-In | 1/8/2004 | 1/28/2004 | 1/28/2004 12:00:00 AM | P | CANC |
|
|
resched 2/19/04 am 1/28/2004 9:29:26 AM
|