PLM05-00250
| Sprinkler (Final) | 1/27/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | A | PASS |
|
|
renee; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
PLM04-03357
| Water and/or Sewer | 1/27/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | A | CANC |
|
|
Contact Perry with questions; Phone #: ###-#### Internet Inspection Request from: Roger Patterson
|
PLM04-03357
| Final | 1/27/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | A | PASS |
|
|
Perry; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
PLM05-00181
| Plumbing Rough-in | 1/27/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | A | PASS |
|
|
Internet Inspection Request from: Kim Alderson
|
PLM04-00501
| Final | 1/27/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 11:22:04 PM. Contact: ###-####. upc 409.1 water closet bowls for public use to be elongated type with open front seat (2) need to provide a PVB on hand held shower at hydroco table (3) have all backflow devices tested and certified (4) provide clearance and acess for testing and maintenance and repair for double check,s located in wall 1/28/2005 11:36:43 AM
|
PLM04-03441
| Final | 1/28/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 1/28/2005 at 7:41:19 AM. Contact: ###-####.
|
PLM05-00256
| Plumbing Rough-in | 1/28/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | P | FAIL |
|
|
leo ###-#### in unit 8513- need to remove fernco coupling from 3 inch pipe in over head and replace with approved coupling 2- need to roll island sink vent connection to drain line above center line and support island sink vent in floor joist every 4 feet also need a few more hanger,s on drain lines in crawl in unit 8517 need to move water piping 12 inches away from can lighting in overhead in kitchen area and test failed on DWV . left notice and called contractor will recall when ready 1/28/2005 2:41:58 PM
|
PLM04-03265
| Final | 1/28/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 1/28/2005 at 11:13:38 AM. Contact: ###-####.
|
PLM05-00248
| Plumbing Rough-in | 1/28/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | P | PASS |
|
|
|
PLM05-00238
| Plumbing Rough-in | 1/27/2005 | 1/28/2005 | 1/28/2005 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 6:32:22 PM. Contact: ###-####. correct all leaks and retest correct reverse grade in 3 inch under kit area in crawl space support pvc DWV as per table 3-2 in 2003 upc talked to contractor on job site will recall when ready 1/28/2005 4:27:28 PM
|