FIR10-00503
| FIR-Aging Inspection | 1/28/2011 | 1/28/2011 | 2/1/2011 4:27:03 PM | | PART |
|
|
In progress
|
BLD10-01058
| FIRE-Final Inspection | 1/27/2011 | 1/28/2011 | 1/28/2011 2:56:54 PM | A | FAIL |
|
|
Post two fire extinguishers as discussed, install one exit sign at the second classroom exit door per plan. Mechanical inspector to review damper installation.
|
FIR10-00495
| INSP-Final Inspection | 1/27/2011 | 1/28/2011 | 1/28/2011 2:44:33 PM | A | PART |
|
|
Verified previous correction items have been finished, noted system is missing inspectors test connection including valve and test orfice, partition walls at the first floor offices are not yet installed, missing ceiling tile, provide current inspection tags at the riser. Tamper switches at control valves tested okay.
|
FIR11-00024
| INSP-Final Inspection | 1/27/2011 | 1/28/2011 | 1/28/2011 2:37:09 PM | A | FAIL |
|
|
Noted items include: Provide plan modification resubmittals for added duct detectors at RTU's per review comments, elevator control functions test pending repair of shunt trip, RTU units 6 and 8 appear to have damaged relays at detector housings, missing inspectors test at the sprinkler system for the flow switch, post signage at the door to the FACP room per review note #22, provide points map at the panel.
|
BLD10-02937
| FIRE-Final Inspection | 1/28/2011 | 1/28/2011 | 1/28/2011 2:20:47 PM | P | PASS |
|
|
Fire life safety inspection passed. Contractor to repair one existing EM light today as agreed.
|
BLD11-00057
| FIRE-Final Inspection | 1/27/2011 | 1/28/2011 | 1/28/2011 10:45:30 AM | A | PASS |
|
|
Corrections per previous inspection completed by S. Arellano verified for completion. Contractor to post building address numbers(1712) today as agreed.
|
FIR10-00653
| INSP-Final Inspection | 1/26/2011 | 1/28/2011 | 1/28/2011 10:40:04 AM | A | NR |
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
FIR10-00355
| INSP-Final Inspection | 1/26/2011 | 1/28/2011 | 1/28/2011 10:37:47 AM | A | NR |
|
|
Need to complete 24 hr. air test of the new dry system per NFPA 13 2007 24.2.2.1
|
FIR10-00646
| INSP-Final Inspection | 1/27/2011 | 1/28/2011 | 1/27/2011 6:56:45 PM | A | CANC |
|
|
A portion of the space is occuppied by other tenants, could we schedule it for early morning (prior to 8am) so as not to disrupt business? Phone #: ###-#### >> Inspection requested via web by Jeff Durham Inspection cancelled from web by: Jeff Durham
|
FIR10-00415
| INSP-Final Inspection | 1/27/2011 | 1/28/2011 | 1/27/2011 3:18:49 PM | A | CANC |
|
|
Request for 7:30am inspection. Rafe with Protex is the contat, his cell no. is ###-####. Phone #: ###-#### >> Inspection requested via web by Shawna Gates Inspection cancelled from web by: Shawna Gates
|