FIR14-00939
| INSP-Sprinkler Rough-in | 1/28/2015 | 1/28/2015 | 1/28/2015 4:05:21 PM | P | PART |
|
|
Overhead fire sprinkler work approved for cover.
|
FIR14-00938
| INSP-Sprinkler Rough-in | 1/28/2015 | 1/28/2015 | 1/28/2015 3:22:59 PM | P | PART |
|
|
Rough-in inspection passed, okayed for ceiling after coverage adjustment completed while on site.
|
BLD15-00156
| FIRE-Final Inspection | 1/28/2015 | 1/28/2015 | 1/28/2015 3:20:13 PM | P | PASS |
|
|
Life safety inspection passed. Property manager to repair two exit signs and two EM lights at the common corridor as discussed.
|
FIR14-00937
| INSP-Sprinkler Rough-in | 1/28/2015 | 1/28/2015 | 1/28/2015 3:16:26 PM | P | PART |
|
|
Overhead fire sprinkler work approved for cover at the drop ceiling.
|
FIR14-00935
| INSP-Sprinkler Rough-in | 1/28/2015 | 1/28/2015 | 1/28/2015 3:15:18 PM | P | PART |
|
|
Rough-in okay for cover pending plan modification to match field install regarding branch line and head locations.
|
FIR14-00252
| INSP-Sprinkler Rough-in | 1/28/2015 | 1/28/2015 | 1/28/2015 3:12:54 PM | P | PART |
|
|
Rough-in for cover finished at the 1st floor kitchen lobby area, okayed SW coverage adjacent to the fireplace. Noted cold solder issues at sprinklers each side of beam pockets.
|
NAF15-00001
| INSP-Sprinkler Rough-in/Hydro | 1/28/2015 | 1/28/2015 | 1/28/2015 3:09:44 PM | A | PART |
|
|
UG fire supply line okayed for cover per inspection completed by T. Cobbley 1/27 at the initial visit for the hydrostatic test.
|
FIR14-00708
| INSP-Sprinkler Rough-in | 1/27/2015 | 1/28/2015 | 1/27/2015 10:11:11 AM | P | CANC |
|
|
3rd floor balcony RTC Call Leroy 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|