FIR02-00263
| INSP-Sprinkler Rough-in/Hydro | 1/28/2003 | 1/29/2003 | 1/29/2003 12:00:00 AM | A | PART |
|
|
###-####. Sprinkler piping is ok to cover from the west side fire doors all the way to the end of the building except for the west elevator lobby. One storage room and a cleaner storage room have sprinkler heads that are over spaced and several hangers need to be added. These locations are marked on the approved sprinkler drawings. 1/29/2003 10:27:22 AM
|
MIS02-00213
| FIR-Final | 1/28/2003 | 1/29/2003 | 1/29/2003 12:00:00 AM | A | PASS |
|
|
fire life safety and fire sprinkler finaled 1/29/2003 12:21:56 PM
|
BLD02-02753
| FIRE-Final Inspection | 1/29/2003 | 1/29/2003 | 1/29/2003 12:00:00 AM | P | FAIL |
|
|
Phone #: ###-#### Provide fire dept. plan review notes. Plug pendant that is above ceiling. Provide lever hardware on the five doors in the remodeled area 1/29/2003 1:32:09 PM
|
FIR02-00414
| INSP-Alarm Testing | 1/28/2003 | 1/29/2003 | 1/29/2003 12:00:00 AM | P | FAIL |
|
|
Retest nitrogen pressure switch, IR detector alarm comes in as a supervisory, loss of power to tool comes in as a supervisory but should be a trouble, loss of power to the IR detector comes in as a supervisory instead of a trouble, These items and the items on the review notes NOT marked with an OK need to be tested 1/29/2003 4:35:19 PM 1/29/2003 4:40:13 PM
|