Inspections for the day of: Monday, January 29, 2007.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00942 INSP-Alarm Testing1/25/20071/29/20071/30/2007 9:28:39 AMPFAIL
SD at the elevator lobby failed to recall the car, need to test the hood suppression system interconnection, provide access for testing of the PIV tamper, noted one duct detector in need of revision of sample and vent tube orientation (repaired while on site), remove the duct insulation liner at the vent tube on the remaining duct detectors. The panel, manual pull, SD at panel, waterflow and sprinkler main control tested okay. Also need verification of signals recieved as discussed.
FIR06-00476 INSP-Final Inspection1/25/20071/29/20071/29/2007 3:30:01 PMPNR
Noted the UG supply line flush must be completed prior to overhead final.
FIR05-00737 INSP-Final Inspection1/25/20071/29/20071/29/2007 3:14:22 PMPDEFR
Inspection rescheduled.
FIR05-00425 INSP-Sprinkler Rough-in/Hydro1/29/20071/29/20071/29/2007 3:11:28 PMPPART
Mechanical room hydrostatic test and the conclusion of the tank hydro both completed satisfactory.
FIR06-00992 INSP-Sprinkler Rough-in/Hydro1/29/20071/29/20071/29/2007 2:56:19 PMPPART
OH sprinkler rough-in is approved for cover at the hard lid ceilings.
BLD06-01521 FIRE-Final Inspection1/29/20071/29/20071/29/2007 2:08:52 PMPPASS
Items on c/n have been verified for completion, life safety finaled.
FIR07-00004 INSP-Sprinkler Rough-in/Hydro1/26/20071/29/20071/29/2007 1:26:33 PMPNR
Required work is not yet complete for inspection.
FIR06-00883 INSP-Final Inspection1/29/20071/29/20071/29/2007 1:25:15 PMPPASS
Fire alarm permit finaled.
FIR06-00129 INSP-Final Inspection1/29/20071/29/20071/29/2007 1:24:44 PMPPASS
Fire alarm permit finaled.
FIR06-00728 INSP-Supply line flush1/26/20071/29/20071/29/2007 1:24:21 PMPPART
UG supply line flush completed satisfactory, noted control valve manifold at the 2nd floor to be repiped for the provision of adequate and reasonable access.
FIR06-00999 INSP-Final Inspection1/26/20071/29/20071/29/2007 12:13:20 PMPCANC
Inspection canceled per contractor.
FIR06-00946 INSP-Final Inspection1/26/20071/29/20071/29/2007 12:12:47 PMPCANC
Cancel inspection per contractor.
FIR06-00883 INSP-Alarm Testing1/25/20071/29/20071/29/2007 12:12:02 PMAPASS
Fire alarm work passed field inspection.
FIR06-00129 INSP-Alarm Testing1/25/20071/29/20071/29/2007 12:11:03 PMAPASS
The remainder of FA devices at the remodel area tested approved, permit finaled.
FIR06-00770 INSP-Sprinkler Rough-in1/26/20071/29/20071/29/2007 12:08:43 PMAPART
Fire sprinkler rough-in is good for cover at the drop ceiling areas as circled and initialed on approved plans.
BLD06-02184 FIRE-Final Inspection1/26/20071/29/20071/29/2007 11:03:14 AMAFAIL
Fire alarm modifications are necessary which will require a permit and inspection for approval prior to life safety final, also need to provide one PFE, repair emergency lights at the exercise room, provie approved door hardware at two locations, post max occupant load sign, provide signage above keyed locking doors.