BLD08-02196
| BLD-Energy code compliance | 1/29/2009 | 1/29/2009 | 1/29/2009 3:47:26 PM | P | PASS |
|
|
Jim Phone #: ###-####. Rigid foam insul. on interior side of stemwall.
|
BLD08-02195
| BLD-Energy code compliance | 1/29/2009 | 1/29/2009 | 1/29/2009 3:46:57 PM | P | PASS |
|
|
Jim Phone #: ###-####. Rigid foam insul on interior side of stemwall. ok.
|
BLD08-02194
| BLD-Energy code compliance | 1/29/2009 | 1/29/2009 | 1/29/2009 3:46:27 PM | P | PASS |
|
|
Jim Phone #: ###-####. Rigid foam insul. on interior side of stemwall. ok.
|
BLD08-02186
| BLD-Energy code compliance | 1/29/2009 | 1/29/2009 | 1/29/2009 3:18:36 PM | P | PASS |
|
|
Jim Phone #: ###-####. rigid foam insul. on interior side of stemwall. ok.
|
BLD08-02187
| BLD-Energy code compliance | 1/29/2009 | 1/29/2009 | 1/29/2009 3:17:31 PM | P | PASS |
|
|
Jim Phone #: ###-####. Rigid foam insul. on interior side of stemwall. ok.
|
ESC08-00877
| Random Inspection | 1/29/2009 | 1/29/2009 | 1/29/2009 3:16:06 PM | P | PART |
|
|
wip on sweeping and scraping sediment from sidewalk and gutterpan.
|
BLD08-02188
| BLD-Energy code compliance | 1/29/2009 | 1/29/2009 | 1/29/2009 3:15:29 PM | P | PASS |
|
|
Jim Phone #: ###-####. Rigid foam insul. on interior side of stemwall.
|
ESC08-00878
| Random Inspection | 1/29/2009 | 1/29/2009 | 1/29/2009 3:13:57 PM | P | PART |
|
|
wip on sweeping and scraping sediment from gutterpan.
|
ESC08-00879
| Random Inspection | 1/29/2009 | 1/29/2009 | 1/29/2009 3:13:21 PM | P | PART |
|
|
Wip on sweeping and scraping sediments from sidewalk and gutter pan.
|
BLD08-02189
| BLD-Energy code compliance | 1/29/2009 | 1/29/2009 | 1/29/2009 3:12:11 PM | P | PASS |
|
|
Jim Phone #: ###-####. Rigid foam insul at interior side of stemwall. ok.
|
ESC08-00876
| BMP Violation | 1/29/2009 | 1/29/2009 | 1/29/2009 2:09:26 PM | P | PASS |
|
|
Trash has been containerized and di protection installed. ok.
|
ESC08-00897
| Tracking Control | 1/29/2009 | 1/29/2009 | 1/29/2009 1:56:52 PM | P | PART |
|
|
Contractor has made significant progress in cleanup. wip. Contractor has also hired ground effects, they were replacing di protection and providing waddels while on site.
|
BLD08-02203
| BLD-Foundation | 1/29/2009 | 1/29/2009 | 1/29/2009 1:55:09 PM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 1/29/2009 at 7:38:41 AM. Contact: ###-####.
|
ESC08-00898
| Tracking Control | 1/29/2009 | 1/29/2009 | 1/29/2009 1:54:54 PM | P | PART |
|
|
Contractor has made significant progresss in clean up. wip. Noted the contractor has hired ground effects, they were replacing di protection and providing waddels.
|
BLD08-02204
| BLD-Foundation | 1/29/2009 | 1/29/2009 | 1/29/2009 1:53:05 PM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 1/29/2009 at 7:39:26 AM. Contact: ###-####.
|
ESC08-00895
| Tracking Control | 1/29/2009 | 1/29/2009 | 1/29/2009 11:19:40 AM | A | PART |
|
|
contractor has made significant progress on cleanup. wip. Noted that contractor has hired an ground effects, they were replacing di protection when on site and delivering wadels.
|
BLD08-02201
| BLD-Foundation | 1/29/2009 | 1/29/2009 | 1/29/2009 11:17:58 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 1/29/2009 at 7:29:54 AM. Contact: ###-####.
|
ESC08-00896
| Tracking Control | 1/29/2009 | 1/29/2009 | 1/29/2009 11:17:38 AM | A | PART |
|
|
Contractor has made significant progress on cleanup. wip. Contractor has also hired ground effects, they were on site installing new inlet protection and delevering waddels. street has been cleaned.
|
BLD08-02202
| BLD-Foundation | 1/29/2009 | 1/29/2009 | 1/29/2009 11:15:20 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 1/29/2009 at 7:30:46 AM. Contact: ###-####.
|
ESC09-00010
| Site Preparation | 1/29/2009 | 1/29/2009 | 1/29/2009 10:10:08 AM | A | FAIL |
|
|
Needs to provide drain inlet protection in front of house. Contain excavated soils or remove them immediatly. Also needs to sweep and scrape sediment from sidewalk and gutter pan. Will reinspect on 1/30/09. A c/n was isued. Non compliance will result in stop work order.
|
BLD09-00042
| BLD-Footing | 1/28/2009 | 1/29/2009 | 1/29/2009 10:07:12 AM | A | PASS |
|
|
sebastian Phone #: ###-####
|
BLD08-01846
| BLD-Final | 1/28/2009 | 1/29/2009 | 1/29/2009 9:52:31 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 1/28/2009 at 9:56:45 AM. Contact: ###-####. Needs to extend curb protection on ramp from were modular building ends. Refer to to aproved plans for handrail extensions. Installed handrail is not code compliant. c/n issued. Also contacted contractor.
|
BLD09-00006
| BLD-Footing | 1/28/2009 | 1/29/2009 | 1/29/2009 12:00:00 AM | A | CANC |
|
|
wade Note: pour at 9:00 am Phone #: ###-####
|