BLD13-00002
| FIRE-Final Inspection | 1/29/2013 | 1/29/2013 | 1/30/2013 5:44:57 PM | P | NR |
|
|
|
BLD12-02718
| FIRE-Conference | 1/29/2013 | 1/29/2013 | 1/29/2013 4:11:13 PM | P | DONE |
|
|
|
FIR12-00731
| INSP-Sprinkler Rough-in | 1/29/2013 | 1/29/2013 | 1/29/2013 4:10:33 PM | P | PART |
|
|
UG fire supply line approved for bury.
|
BLD13-00005
| FIRE-Final Inspection | 1/28/2013 | 1/29/2013 | 1/29/2013 4:09:25 PM | P | PASS |
|
|
C/N items verified. Tenant to post signage prior to structural final. Life safety passed.
|
FIR13-00019
| INSP-Sprinkler Rough-in | 1/29/2013 | 1/29/2013 | 1/29/2013 3:29:17 PM | P | PART |
|
|
Overhead fire sprinkler system modifications approved for cover at the drop ceilings.
|
BLD13-00075
| FIRE-Final Inspection | 1/28/2013 | 1/29/2013 | 1/29/2013 2:22:36 PM | A | FAIL |
|
|
Refer to items # 4 and 5 on the permit documents general conditions page, need to provide current tag on the fire extinguisher, verify FP system is also current with an annual inspection, repair EM lighting, remove or repair non-required exit signs.
|
BLD12-02524
| FIRE-Final Inspection | 1/29/2013 | 1/29/2013 | 1/29/2013 2:02:04 PM | P | NR |
|
|
|
BLD12-02524
| FIRE-Alarm Testing | 1/29/2013 | 1/29/2013 | 1/29/2013 1:09:14 PM | P | NR |
|
|
Project related fire alarm permit is not yet issued.
|
FIR12-00679
| INSP-Sprinkler Rough-in | 1/28/2013 | 1/29/2013 | 1/29/2013 11:59:42 AM | A | PART |
|
|
UG fire supply line thrust blocking verified,- okay to bury. Discussed seismic clearance at the ductile riser when floor slab is poured.
|
BLD13-00084
| FIRE-Final Inspection | 1/28/2013 | 1/29/2013 | 1/29/2013 11:55:50 AM | A | PASS |
|
|
Verified correction items. Fire life safety passed.
|