FIR18-00610
| INSP-Sprinkler Rough-in | 1/29/2019 | 1/29/2019 | 1/29/2019 4:49:42 PM | P | PART |
|
|
Overhead fire sprinkler piping located above hardlids in level 2 restrooms and level 1 entry hardlids complete, areas inspected approved for cover.
Second floor restrooms rough to cover // Mike Phone #: ###-####
|
FIR19-00051
| INSP-Final Inspection | 1/29/2019 | 1/29/2019 | 1/29/2019 2:45:43 PM | P | PASS |
|
|
Final communicator inspection complete.
Phone #: ###-#### Inspection requested via web by John Siewert
|
FIR18-00790
| INSP-Final Inspection | 1/29/2019 | 1/29/2019 | 1/29/2019 2:45:15 PM | P | PASS |
|
|
Final hood suppression inspection complete.
Phone #: 2089546009 >> Inspection requested via mobile web by Kenny Leslie
|
BLD19-00227
| FIRE-Final Inspection | 1/28/2019 | 1/29/2019 | 1/29/2019 1:21:28 PM | P | FAIL |
|
|
Provide sugnage on main entry reading door to remain unlocked while building is occupied. Slide bolt locks on rear door need to be removed to be code compliant.
Dana or Amanda Phone #: ###-####
|
FIR18-00673
| INSP-Sprinkler Rough-in/Hydro | 1/29/2019 | 1/29/2019 | 1/29/2019 12:12:16 PM | A | FAIL |
|
|
Hydrostatic test for wet system lost 4 psi during test, te-hydro is required.
|
FIR18-00847
| INSP-Final Inspection | 1/29/2019 | 1/29/2019 | 1/29/2019 12:10:08 PM | P | PASS |
|
|
Final fire sprinkler inspection for area of work complete.
We would like to perform this inspection in coordination with fire life safety for BLD. Please call Rick with Questions. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
BLD18-03237
| FIRE-Final Inspection | 1/28/2019 | 1/29/2019 | 1/29/2019 11:27:59 AM | A | FAIL |
|
|
Access control door to the right of the main entry when entering space appears to not be connected to the fire alarm panel, access control needs to de-energize during general fire alarm.
Garret Phone #: ###-####
|
FIR18-00510
| INSP-Sprinkler Rough-in/Hydro | 1/28/2019 | 1/29/2019 | 1/29/2019 11:23:23 AM | A | PART |
|
|
Rough to cover inspection for levels 2 and 3 complete, approved for cover.
Third floor hydro. Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR18-00673
| INSP-Sprinkler Rough-in/Hydro | 1/26/2019 | 1/29/2019 | 1/29/2019 10:38:18 AM | A | PART |
|
|
24 hour ait test started at 10AM with 40 psi on all three dry systems.
Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
FIR18-00827
| INSP-Sprinkler Rough-in | 1/24/2019 | 1/29/2019 | 1/29/2019 10:15:25 AM | A | FAIL |
|
|
Point of contact could not be reached.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00544
| INSP-Supply line flush | 1/24/2019 | 1/29/2019 | 1/29/2019 10:15:04 AM | A | FAIL |
|
|
Point of contact could not be reached.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00545
| INSP-Supply line flush | 1/24/2019 | 1/29/2019 | 1/29/2019 10:14:37 AM | A | FAIL |
|
|
Point of contact could not be reached.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00519
| INSP-Supply line flush | 1/24/2019 | 1/29/2019 | 1/29/2019 10:14:11 AM | A | FAIL |
|
|
Point of contact could not be reached.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00562
| INSP-Supply line flush | 1/24/2019 | 1/29/2019 | 1/29/2019 10:13:48 AM | A | FAIL |
|
|
Point of contact could not be reached.
Gerarrdo is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD18-03965
| FIRE-Final Inspection | 1/29/2019 | 1/29/2019 | 1/29/2019 10:12:51 AM | A | PASS |
|
|
Previously oted items have been corrected, final life fire safety inspection for area of work.
|
FIR17-00508
| INSP-Alarm Testing | 1/28/2019 | 1/29/2019 | 1/29/2019 10:12:10 AM | A | FAIL |
|
|
Address numbers on tampers do not match city approved drawings. Trouble with remote mic, need to resolve issues. As-builts need to be sent to fire alarm plan reviewer.
TCO for area A Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
FIR17-00474
| INSP-Final Inspection | 1/28/2019 | 1/29/2019 | 1/29/2019 10:12:09 AM | A | PART |
|
|
Fire sprinkler inspection for TCO phase 1 complete.
Contact is Mark Jensen. Thank you for your help! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR19-00018
| INSP-Sprinkler Rough-in | 1/28/2019 | 1/29/2019 | 1/29/2019 8:20:21 AM | A | FAIL |
|
|
All tenting not installed at time of inspection.
Tenting Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
FIR19-00010
| INSP-Final Inspection | 1/25/2019 | 1/29/2019 | 1/29/2019 8:07:02 AM | A | FAIL |
|
|
Appliance under hood did not de-energize when hood system activated, per code all energy sources need to be isolated under the hood during system activation.
Coordinated with Jim Page, to do inspection at 8 am! Thanks! -Zach w/ Firexpert. Phone #: ###-#### Inspection requested via web by Don Kartchner
|