BLD00-03140
| BLD-Final | 1/29/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | A | PASS |
|
|
###-#### Rex... Per approved plans re property lines, openings. ok, l/c issued. 1/30/2001 10:27:01 AM
|
BLD00-03185
| BLD-Footing | 1/29/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 01/29/2001 at 14:43:13. Contact: ###-####. mti report pending...need surveyors statement for p.l. 1/30/2001 9:43:43 AM
|
BLD00-01970
| BLD-Final | 1/29/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | A | PASS |
|
|
Glenn Anderson ###-####
|
BLD00-02123
| BLD-Final | 1/29/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | A | NR |
|
|
FN INSP- ###-####- STEVEN conf only w/ owner 1/30/2001 10:07:32 AM
|
BLD00-03650
| BLD-Conference | 1/30/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 340 On 1/30/2001 11:11:06 AM w/ owner, insul installed at ext; complete framing & call for insp.
|
BLD00-02123
| BLD-Framing/Rough-in | 1/30/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | A | FAIL |
|
|
Added by Inspector: 340 On 1/30/2001 10:09:04 AM roof rebuild appears ok, nail-off sheathing,obtain other insps...ok to continue perconference w/ owner
|
BLD00-00771
| BLD-Framing/Rough-in | 1/30/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | P | PART |
|
|
Paul ###-#### ok to cover high ceiling & upper 1/2 demising wall at 1/30/2001 5:14:30 PM 2nd fl. 1/30/2001 5:21:02 PM
|
BLD00-01563
| BLD-Concrete | 1/29/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 01/29/2001 at 06:35:07. Contact: ###-####... pending spec. insp report 1/30/2001 1:54:47 PM
|
BLD00-03190
| BLD-Framing/Rough-in | 1/30/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | P | PART |
|
|
###-#### c/n ok, unable to access underfloor, chk at final or? 1/30/2001 3:19:45 PM ok to cover 1/30/2001 3:20:03 PM
|
BLD00-03190
| BLD-Energy code compliance | 1/30/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | P | PART |
|
|
check underfloor, attic at final 1/30/2001 3:20:33 PM
|
BLD00-03191
| BLD-Framing/Rough-in | 1/30/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | P | PART |
|
|
Added by Inspector: 340 On 1/30/2001 3:19:03 PM c/n issued, fireblocks, install int. shear etc. ok to insul pending hvac ok
|
BLD00-01903
| BLD-Final | 1/30/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | P | FAIL |
|
|
###-#### HOUSE IS OPEN AND CARPET GUYS ARE THERE., need driveway or bond? 1/30/2001 4:05:31 PM
|
BLD01-00184
| BLD-Footing | 1/29/2001 | 1/30/2001 | 1/30/2001 12:00:00 AM | P | NR |
|
|
###-#### , mono-slab, need plbg r/i...thaw ground & protect concrete from freeze when pouring. 1/30/2001 10:43:58 AM excavation nly looks ok; insulate slab 1/30/2001 10:44:29 AM
|