BLD11-02898
| FIRE-Final Inspection | 1/27/2012 | 1/30/2012 | 1/30/2012 3:50:02 PM | P | PASS |
|
|
life safety passed
|
BLD12-00132
| FIRE-Final Inspection | 1/30/2012 | 1/30/2012 | 1/30/2012 3:01:41 PM | P | FAIL |
|
|
Provide single action hardware on the rear exit door and repair the exit sign/emergency light located directly above this door.
|
BLD11-02911
| FIRE-Final Inspection | 1/30/2012 | 1/30/2012 | 1/30/2012 3:00:40 PM | P | PASS |
|
|
Life safety passed. An additional fire extinguisher is required on the second floor. Per Elizabeth the fire extinguisher would be installed prior to the building inspector sign off.
|
FIR12-00004
| INSP-Final Inspection | 1/25/2012 | 1/30/2012 | 1/30/2012 2:04:12 PM | P | PASS |
|
|
permit finaled
|
FIR11-00563
| INSP-Sprinkler Rough-in/Hydro | 1/27/2012 | 1/30/2012 | 1/30/2012 2:03:25 PM | A | PASS |
|
|
See the city approved plans for the specific rooms where sprinkler piping can be covered. The include the rooms at the west end of the third floor.
|
BLD11-02455
| FIRE-Conference | 1/27/2012 | 1/30/2012 | 1/30/2012 1:28:48 PM | A | DONE |
|
|
On site visit with contractor regarding fire code review note items and project finish schedule.
|
BLD11-01891
| FIRE-Final Inspection | 1/27/2012 | 1/30/2012 | 1/30/2012 10:27:51 AM | A | PASS |
|
|
life safety passed
|
BLD12-00116
| FIRE-Final Inspection | 1/30/2012 | 1/30/2012 | 1/30/2012 9:47:18 AM | P | PASS |
|
|
life safety passed
|