Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR13-00003 INSP-Sprinkler Rough-in1/30/20131/30/20131/30/2013 3:49:03 PMPPASS
Rough-in passed. Piping can be covered.
BLD12-02789 FIRE-Final Inspection1/29/20131/30/20131/30/2013 3:08:24 PMACANC
John Mead Phone #: ###-####
FIR12-00545 INSP-Final Inspection1/30/20131/30/20131/30/2013 2:48:06 PMPPART
A temporary approval is being given, with scott arellano's permission, until the plan modifications are submitted, approved and re-inspected is needed. All devices as installed have been tested. This temporary approval is separate from any occupancy request.
BLD12-02207 FIRE-Final Inspection1/30/20131/30/20131/30/2013 2:44:23 PMPPASS
life safety passed
BLD12-02894 FIRE-Conference1/29/20131/30/20131/30/2013 2:32:57 PMADONE
John and I went over life safety requirements.
FIR12-00395 INSP-Final Inspection1/29/20131/30/20131/30/2013 11:53:41 AMAPASS
permit finaled
BLD12-03070 FIRE-Final Inspection1/29/20131/30/20131/30/2013 10:17:09 AMAPASS
Life safety passed. No materials (gases) are on site for storage arrangement verification.
BLD12-02524 FIRE-Final Inspection1/29/20131/30/20131/30/2013 8:58:24 AMAPASS
Life safety passed
FIR13-00039 INSP-Final Inspection1/29/20131/30/20131/30/2013 8:57:39 AMAPASS
Permit finaled
BLD12-03046 FIRE-Final Inspection1/29/20131/30/20131/30/2013 8:04:30 AMAPASS
life safety passed