BLD13-02197
| BLD-Framing/Rough-in | 1/30/2014 | 1/30/2014 | 1/30/2014 8:13:37 PM | P | PART |
|
|
nate Phone #: ###-####, need to brace interior walls per plans,, all else ok
|
BLD13-01458
| BLD-Framing/Rough-in | 1/30/2014 | 1/30/2014 | 1/30/2014 8:10:08 PM | P | NR |
|
|
Phone #: ###-#### >> Inspection requested via web by James Greenwood,, walk through only,, need fireplace approval,, need plans,, straps,, etc..
|
BLD13-02569
| BLD-Framing/Rough-in | 1/30/2014 | 1/30/2014 | 1/30/2014 8:05:22 PM | P | NR |
|
|
matt Phone #: ###-####,, walk through only
|
BLD13-03091
| BLD-Final | 1/28/2014 | 1/30/2014 | 1/30/2014 1:03:56 PM | A | DONE |
|
|
Final Roof inspection. Call Justin Barker ###-#### if there are question. Phone #: ###-#### x125 >> Inspection requested via web by justin barker
|
BLD13-03091
| DOC - Permit Finaled | 1/30/2014 | 1/30/2014 | 1/30/2014 1:02:42 PM | P | PASS |
|
|
done
|
BLD13-02197
| BLD-Framing/Rough-in | 1/29/2014 | 1/30/2014 | 1/30/2014 12:42:01 PM | A | PART |
|
|
nate Phone #: ###-####,, main floor interior walls ok to cover,, per plan
|
BLD13-03511
| BLD-Final | 1/29/2014 | 1/30/2014 | 1/30/2014 11:21:38 AM | A | DONE |
|
|
>> Inspection requested via web by Michelle Flynn,, roof has been installed
|
BLD13-03511
| DOC - Permit Finaled | 1/30/2014 | 1/30/2014 | 1/30/2014 11:21:16 AM | P | PASS |
|
|
done
|
BLD13-03113
| BLD-Energy code compliance | 1/28/2014 | 1/30/2014 | 1/30/2014 11:02:46 AM | A | PASS |
|
|
call 1/2 hr to meet for access // Raider Phone #: ###-####
|
BLD14-00029
| BLD-Energy code compliance | 1/29/2014 | 1/30/2014 | 1/30/2014 10:28:59 AM | A | PASS |
|
|
Energy as well - Mark Phone #: ###-####
|