ESC14-00608
| Tracking Control | 1/30/2015 | 1/30/2015 | 1/30/2015 4:41:07 PM | P | PASS |
|
|
Corrections requested 1/28 completed:
Old Hickory has been swept and west entrance blocked off. No new trackout or other issues observed.
|
ESC14-00662
| General Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 4:39:26 PM | | PASS |
|
|
No issues at DH#12 staging area. Warm Springs is free of trackout, no discharges and stormdrain system has BMPs and does drain to the pasture north of Warm Sprngs.
Old Hickory has been recently swept and west entrance blocked off per CN issued on ESC14-00608
|
ESC14-01157
| Tracking Control | 1/29/2015 | 1/30/2015 | 1/30/2015 4:39:13 PM | A | CANC |
|
|
rescheduled.
|
ESC14-00661
| General Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 4:12:48 PM | | PASS |
|
|
Disturbed area for greenhouse installation is complete. ESC permit conditions satisfied.
|
ESC14-00661
| DOC - Permit Finaled | 1/30/2015 | 1/30/2015 | 1/30/2015 4:12:17 PM | P | PASS |
|
|
|
ESC14-00664
| General Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 2:50:28 PM | | PASS |
|
|
WIP on building hillside retaining walls. Permit posted, heavy dury construction entrance/tracking pad is instsalled. Downslope perimeter has trenched in wattles and chain link fence to make physical barrier for limits of disturbance. Very good hillside residential ESC BMPs implemented here.
|
ESC14-00892
| Random Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 1:37:23 PM | P | PASS |
|
|
New street curbing on Malad is complete and has been swept and cleaned. Access road to the subdivsion is paved and site utilities and drainage are also installed. Currently no activity, but the site has been left clean and dirt in central area is below grade of curbing so works to contain runoff and sediment.
No corrections needed, approved.
|
ESC14-00432
| Tracking Control | 1/30/2015 | 1/30/2015 | 1/30/2015 12:44:23 PM | P | PART |
|
|
Work has resumed at Aralar subdivision with Idaho Sand Gravel on site excavating roads. New construction entrance has been installed on the south side of 5 Mile Creek but the muddy conditions and truck traffic has created significant trackout onto Lazaro and westbound lanes of Overland. Need to clean up the bicycle lanes.
Driving to other site, noticed issue. Upon return a sweeper was in operation addressing the trackout - so they are being proactive.
Corrections: 1. Lengthen south construction entrance ( too short) 2. Repair north construction entrance 3. Continue regular sweeping
|
ESC13-01323
| General Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 12:26:05 PM | P | PASS |
|
|
Cantabria apartments subdivision is in process of being graded and the pool/community house is being built currently. Heavy rock construction entrances on Cloverdale and also on Overland. Silt fence BMP lines the canal for sediment protection/designate area of disturbance. Permit and SWPPP on site in trailer. Approved.
|
ESC14-00656
| General Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 11:50:47 AM | | PASS |
|
|
WIP on exeterior of building shell. The silt fence that was no longer needed due to installed curbing has been removed. All storm drain inlets have sediment protection. ESC14-00712 which was for the grading/drainage has been finaled. This permit is for vertical construction and site landscaping. No corrections at this time.
|
ESC14-00712
| DOC - Permit Finaled | 1/30/2015 | 1/30/2015 | 1/30/2015 11:46:58 AM | P | PASS |
|
|
Site grading and drainage is complete - which is what this permit was for on the project. Newly installed inlets have been fitted with sediment filter bags. Vertical construction is now covered under BLD13-002003 / ESC14-00656. No further inspections on this permit. All ESC conditions must be satisfied upon final for ESC14-00656
|
ESC14-00656
| DOC - Permit Finaled | 1/30/2015 | 1/30/2015 | 1/30/2015 11:42:56 AM | P | PASS |
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
ESC14-00408
| General Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 11:03:28 AM | | PASS |
|
|
Construction complete on all 4 Landmark Apartment buildings. Building materials and hard surfaces have been swept. All permits finaled and some apartments already occupied. DI bag will be removed by property management company when the dirty snow pile is finished melting. No further ESC inspections needed.
|
ESC14-00408
| DOC - Permit Finaled | 1/30/2015 | 1/30/2015 | 1/30/2015 11:01:41 AM | P | PASS |
|
|
|
ESC14-00057
| General Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 10:48:01 AM | | PASS |
|
|
WIP on Sleep Country store. Site is separate from the 3 other parcels on this new commercial development - which is not yet stablized and has stockpiles remaining. See ESC13-00592. No trackout, spills, or discharges obesrved. No corrections at this time.
|
ESC14-00565
| Aging Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 9:31:26 AM | | PASS |
|
|
|
ESC14-00529
| General Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 8:39:09 AM | | PASS |
|
|
Work on warehouse frames and rood is in progress. No trackout, no earthwork occuring, and parking lot is already paved. No corrections.
|