BLD02-02753
| FIRE-Final Inspection | 1/30/2003 | 1/31/2003 | 1/31/2003 12:00:00 AM | A | PART |
|
|
Temporary occupancy was given with Dave Millers permission until fire alarm plans have been submitted for the additional duct smoke detector and possibly fire smoke dampers 1/30/2003 1:12:43 PM
|
BLD02-02813
| FIRE-Conference | 1/31/2003 | 1/31/2003 | 1/31/2003 12:00:00 AM | A | DONE |
|
|
I spoke with the contractor, Rick, and told him that the sprinkler riser needs to have its annual inspection as well as the fire sprinkler monitoring system. Also there are new duct smoke detectors on the new hvac system and that they would need to be connected to the existing fire alarm panel and that this work would require approved drawings and permits
|
FIR02-00325
| INSP-Final Inspection | 1/30/2003 | 1/31/2003 | 1/31/2003 12:00:00 AM | P | NR |
|
|
ADT was not ready for the inspection 1/31/2003 2:04:13 PM
|