Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE11-01827 ELE-Aging Inspection1/31/20131/31/20132/1/2013 2:07:55 PM DONE
no work done, still under construction
ELE10-02455 ELE-Aging Inspection1/31/20131/31/20132/1/2013 2:04:26 PM DONE
still uner construction
ELE07-03492 ELE-Aging Inspection1/31/20131/31/20132/1/2013 2:03:14 PM DONE
still under construction
ELE13-00204 Electrical Rough-In1/31/20131/31/20131/31/2013 2:47:17 PMPPASS
Phone #: ###-#### >> Inspection requested via web by PAT MILLER ri ok
ELE13-00203 Temporary Service1/31/20131/31/20131/31/2013 2:36:15 PMPPASS
Phone #: ###-#### >> Inspection requested via web by Darryn Coburn t/s u/g n ok
ELE12-02297 Final1/30/20131/31/20131/31/2013 1:08:46 PMPPASS
Phone #: ###-#### >> Inspection requested via web by ERIC CENTERS ok final
ELE13-00194 Temporary Service1/30/20131/31/20131/31/2013 10:19:13 AMAPASS
Phone #: ###-#### >> Inspection requested via web by Emmet Bushman t/s u/g n ok
ELE13-00195 Temporary Service1/30/20131/31/20131/31/2013 10:06:57 AMAPASS
>> Inspection requested via web by Emmet Bushman t/s u/g n ok
ELE10-02086 Final1/30/20131/31/20131/31/2013 9:38:14 AMAFAIL
jeremy Phone #: ###-#### all receptacles reverse polarity, gfci open ground
ELE13-00188 Rough-In Permanent Service1/30/20131/31/20131/31/2013 9:22:34 AMAPASS
Phone #: ###-#### >> Inspection requested via web by Alan Lusk ri ok, p/s u/g n ok
ELE12-03050 Electrical Rough-In1/30/20131/31/20131/31/2013 8:41:09 AMAPASS
Bob..This is for the second room remodel in Bldg 36...Ken Phone #: ###-#### >> Inspection requested via web by Ken Heller ri ok, ok cover ceiling