Inspections for the day of: Tuesday, January 4, 2000.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorStan Johnson
TitlePLM-INSPECTOR
Phone #340-1257
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM00-00002 Plumbing Rough-in1/3/20001/4/20001/4/2000 12:00:00 AMACANC
###-####. In state.
PLM99-04234 Water and/or Sewer1/3/20001/4/20001/4/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 01/03/2000 at 14:20:06. Contact: ###-####.
PLM99-03899 Plumbing Rough-in1/3/20001/4/20001/4/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 01/03/2000 at 14:28:31. Contact: ###-####.
PLM99-03418 Final1/3/20001/4/20001/4/2000 12:00:00 AMAPASS
###-####-PAT FN GAR CODE 0071 ENTER
PLM99-04229 Plumbing Rough-in1/3/20001/4/20001/4/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 01/03/2000 at 21:44:20. Contact: ###-####.
PLM00-00001 Plumbing Rough-in1/4/20001/4/20001/4/2000 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 01/04/2000 at 07:38:07. Contact: ###-####.--CANCEL PER ARRON WITH MAGIC PLM
PLM99-03784 Final1/4/20001/4/20001/4/2000 12:00:00 AMPPASS
#1869 on garage door\\###-####
PLM00-00009 Plumbing Rough-in1/4/20001/4/20001/4/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 01/04/2000 at 09:17:33. Contact: ###-####.
PLM00-00014 Water and/or Sewer1/4/20001/4/20001/4/2000 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 01/04/2000 at 09:53:00. Contact: ###-####. Flat tire contractor.
PLM99-03603 Final1/4/20001/4/20001/4/2000 12:00:00 AMPNR
Scheduled by a contractor via Hello! on 01/04/2000 at 10:04:34. Contact: ###-####. Floor finish wet.
PLM99-01708 Final1/4/20001/4/20001/4/2000 12:00:00 AMPNH
###-#### key above entry way door. No key found.
PLM99-04186 Plumbing Rough-in1/4/20001/4/20001/4/2000 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 01/04/2000 at 11:06:30. Contact: . Corrections not made $42.00 reinspect. fee.