ELE01-03611
| Final | 1/3/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | A | FAIL |
|
|
###-#### cor. posted called needs outlet right of sliding door Mike K made note of this at time of r/i to contractor 1/4/2002 12:05:13 PM
|
ELE01-03932
| Final | 1/3/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | A | PASS |
|
|
MIKE ###-#### EXT- 104 TRISHA WILL BE AT THE HOUSE ok 1/4/2002 10:27:01 AM
|
ELE01-04328
| Permanent Service | 1/3/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | A | PASS |
|
|
###-#### p/s u/g new ok 1/4/2002 12:38:33 PM
|
ELE01-03838
| Final | 1/3/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/03/2002 at 16:23:10. Contact: ###-####. cor. posted called protect wire, and install proper size box out end of peninsular counter lock out for W H breaker 1/4/2002 11:04:37 AM
|
ELE01-04133
| Electrical Rough-In | 1/3/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | A | PART |
|
|
###-#### met with Dan 1/4/2002 10:02:57 AM
|
ELE01-04133
| Electrical Rough-In | 1/3/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | P | CANC |
|
|
###-#### was in the A M 1/4/2002 2:05:21 PM
|
ELE01-02087
| Final | 1/4/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/04/2002 at 07:44:37. Contact: ###-####. ok 1/4/2002 3:52:44 PM
|
ELE02-00028
| Final | 1/4/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | P | PASS |
|
|
###-#### skip 4 fished in receptacles ok 1/4/2002 2:32:04 PM
|
ELE02-00037
| Electrical Rough-In | 1/4/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | P | FAIL |
|
|
UNDERGROUND FEED TO GARAGE ###-#### covered before inspection called 1/4/2002 11:27:09 AM
|
ELE02-00038
| Electrical Rough-In | 1/4/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | P | FAIL |
|
|
LINE FEED TO GARAGE ###-#### covered before inspection called 1/4/2002 11:26:44 AM
|
ELE01-03838
| Final | 1/4/2002 | 1/4/2002 | 1/4/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/04/2002 at 10:04:09. Contact: ###-####. ok 1/4/2002 2:57:53 PM
|