Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00902 INSP-Sprinkler Rough-in1/3/20061/4/20061/5/2006 3:58:12 PMAPASS
The demo work is complete for the freezer and cooler, coverage at remaining grid ceiling is adequate.
BLD05-00978 FIRE-Final Inspection1/3/20061/4/20061/5/2006 3:29:04 PMAPART
Limited use approval granted with Sam Rogers permission for the covered outside dock structure ONLY. No use or occupancy allowed for the main building at this time.
FIR05-00152 INSP-Sprinkler Rough-in/Hydro1/3/20061/4/20061/4/2006 4:48:33 PMPPART
Hydrostatic test for the UG fire supply line passed inspection.
FIR05-00848 INSP-Final Inspection1/3/20061/4/20061/4/2006 4:40:50 PMAFAIL
Strobe notification devices are not in synchronization within the TI space or within view of the adjacent common area strobes, still need to provide an updated map at the panel as requested, not all smoke alarms tested at this time.
FIR05-00817 INSP-Sprinkler Rough-in/Hydro1/4/20061/4/20061/4/2006 4:35:08 PMPPART
Overhead rough-in is good for cover at the hard lid areas.
FIR05-00594 INSP-Sprinkler Rough-in1/4/20061/4/20061/4/2006 2:11:41 PMPPART
Inspection for rough-in at 2nd floor hard lid area, sprinklers at ceiling pocket areas must comply with the requirements of note #137 on plan review documents. The updated approved resubmitted plans are required for future overhead inspection requests.
FIR05-00840 INSP-Final Inspection1/3/20061/4/20061/4/2006 12:21:48 PMAPART
One arm-over in the exit corridor by the SW stairs needs a hanger, per contractor the heads in the corridor to be relocated to center of ceiling tile per request by owner, some escutcheons in the elevator lobby have sheetrock mud on them.
BLD05-02382 FIRE-Final Inspection12/30/20051/4/20061/4/2006 11:20:16 AMAFAIL
Need to provide a current inspection tag on the fire extinguisher and mount to the wall as discussed along a normal path of travel with the handle no higher than 48" AFF.
BLD05-02877 BLD-Aging Inspection1/4/20061/4/20061/4/2006 10:48:10 AMPPASS
The related fire sprinkler work has been completed, life safety inspection passed.
FIR05-00887 INSP-Final Inspection1/3/20061/4/20061/4/2006 10:28:17 AMAPASS
Sprinkler work passed inspection, noted to the supervisor that a tamper switch for a valve to a hose connection at the riser was closed and reporting to the panel.