BLD15-04206
| FIRE-Final Inspection | 12/31/2015 | 1/4/2016 | 1/4/2016 11:36:27 AM | A | PASS |
|
|
Fire sprinkler inspection complete, fire alarm inspection complete. Life fire safety inspection passed/complete
|
FIR15-00899
| INSP-Final Inspection | 1/4/2016 | 1/4/2016 | 1/4/2016 11:35:29 AM | P | PASS |
|
|
Final fire alarm inspection passed/complete.
|
FIR15-00701
| INSP-Sprinkler Rough-in | 1/4/2016 | 1/4/2016 | 1/4/2016 10:37:51 AM | P | PART |
|
|
First floor rough to cover inspection passed/complete, approved for cover. 2nd floor piping still needs tenting installed, cannot cover 2nd floor piping until tenting is inspected and approved.
|
BLD15-02063
| FIRE-Final Inspection | 12/31/2015 | 1/4/2016 | 1/4/2016 9:07:29 AM | A | FAIL |
|
|
Fire alarm panel located in the south east area of tenant space is not in service, power is shut off to panel and emergency battery back up is depleted, no active fire alarm system at time of inspection, tenant needs to have fire alarm panel serviced/repaired as well as an active monitoring account established. Fire extinguisher in tenant space needs to be serviced and have a current inspection tag installed, tenant needs to have another fire extinguisher installed in tenant space to cover the 75ft travel distance for code compliance. Front entry door has thumb-turn deadbolt, thumb-turn deadolt needs to be changed to a double key deadbolt and signage installed reading "Door to remain unlocked while building is occupied".
|
FIR15-00664
| INSP-Sprinkler Rough-in | 12/31/2015 | 1/4/2016 | 1/4/2016 8:21:14 AM | A | PASS |
|
|
Rough to cover, including tenting for second level piping inspection passed/complete, approved for cover.
|